Wapda again links completion of K-IV to timely funding

Published
0

KARACHI: While a hefty sum of Rs86 billion has been spent on the Greater Karachi Bulk Water Supply Scheme, commonly known as K-IV, the Water and Power Development Authority (Wapda) has once again made it clear that the timely completion of the long-delayed project depends only on the uninterrupted availability of funds.

The fresh assessment by Wapda, which came months after the federal government allocated only Rs3.2 billion against the Rs40bn required for the scheme in the current budget, emerged when its chief, retired Lt Gen Muhammad Saeed, undertook a two-day visit during which he reviewed in detail the construction progress at key sites of the K-IV project.

A statement issued after the visit stated that the Wapda chairman’s programme included the intake structure and pumping stations at Keenjhar Lake in Thatta district, a water conveyance system comprising high-pressure pipelines from Keenjhar Lake to Karachi, and one of the filtration plants in the metropolis.

“During the visit, the General Manager and Project Director, along with the contractors and consultants, briefed the chairman about site-wise as well as contract-wise progress, key targets and their completion schedules,” the statement added.

Overall progress reaches 64pc with Rs86bn spent so far: briefing

“K-IV project has been divided into eight contract packages for its completion on a fast-track basis. At present, construction work is in progress at all key sites of these contract packages. The overall physical progress on the project is 64 per cent, with spending of Rs86 billion. Wapda stands committed to completing K-IV during 2026, provided that the funds are made available accordingly.”

The briefing, the statement said, also encompassed the current financial status and funding requirements for the project in the coming period.

The Wapda chairman, highlighting the critical significance of the project for Karachi, urged the contractors to expedite the pace of work by deploying additional resources to meet the timelines. The contractor working on Pipeline-2 (PL-2), in particular, needs to catch up with the construction schedule of the respective contract package.

He directed the project team to maintain close liaison with the Sindh government for the smooth implementation of the project.

He expressed hope that the provincial government would complete the water distribution and augmentation project in time so that the benefits of K-IV could be fully realised, the statement said.

Published in Dawn, December 1st, 2025

Opinion

Editorial

Fixing bond markets
Updated 01 Oct, 2026

Fixing bond markets

Pension funds, insurance companies, mutual funds, retail investors, and eventually, foreign investors must become bigger participants in the market.
Call centre rackets
01 Oct, 2026

Call centre rackets

A NUMBER of recent raids conducted by the authorities in different cities point to the growing threat fraudulent ...
Homeward bound
01 Oct, 2026

Homeward bound

FIVE months after Somali pirates captured an oil tanker carrying a 19-member multinational crew, Somali maritime...
Kashmir unresolved
Updated 30 Sep, 2026

Kashmir unresolved

The just solution lies in India addressing the issue through a trilateral dialogue involving the legitimate representatives of the Kashmiri people and Pakistan.
Water shortage
30 Sep, 2026

Water shortage

THAT the country is entering the Rabi season with an anticipated water shortage of nearly 25pc, the lowest carryover...
Young hearts
30 Sep, 2026

Young hearts

THE observance may have passed, but the message of World Heart Day should not fade with it. The occasion is a useful...