Wapda takes stock of damage to Neelum-Jhelum dam

Published May 9, 2025
A journalist photographs the damaged wall of the Neelum-Jhelum Hydropower Project in Nausari.—AFP
A journalist photographs the damaged wall of the Neelum-Jhelum Hydropower Project in Nausari.—AFP

MUZAFFARABAD: Water and Power Development Authority (Wapda) Chairman ret­i­red Lt Gen Sajjad Ghani on Thursday visited the Neelum-Jhelum Hydropower Project (NJHP) dam site to assess damage from Indian shelling and to boost the morale of the staff deployed on-site.

The chairman was informed during a detailed inspection of the weir, de-sanders, and intake that the shelling began at 1:15am on May 7 and continued for approximately six hours, ending at 7:15am.

The bombardment damaged a hydraulic power unit of an intake gate and reinforced concrete structures at de-sanders 1 and 3. A residential camp and a medical facility, including an ambulance, were also targeted, according to officials.

Mr Ghani “strongly condemned the Indian attack on the power project,” saying international law, including an additional protocol to the Geneva Conventions of Aug 12, 1949, prohibited attacks on water infrastructure, even during full-scale wars between states.

Attack condemned as ‘act of war’; damage to systems could have triggered ‘massive flooding’

“The coward enemy’s attack is unacceptable and it will be taken up with the respective forums,” he told media at the project site. “It is an act of war which is not acceptable for Pakistan. Even in World War I, World War II and other wars, no one targeted water reservoirs, projects, etc., under norms.”

He said damage to the project’s automated systems could have caused “massive flooding from Muzaffarabad to Mangla”.

“Thank God, our project’s automated system remained safe,” he said. “And had these been affected, there would have been a flood situation from Muzaffarabad to Mangla. Our country escaped a big disaster.”

The Wapda chairman praised the project staff for their “dedication and courage” in taking timely action to protect vital installations. He was accompanied by Muham­mad Arfan Miana, acting member for power and chief executive officer of the NJHP Company, as well as the chief engineer and project director, and the chief engineer for operations and maintenance of the project.

A day earlier, ISPR Director Gen­eral Lt Gen Ahmed Sharif Chaudhry also condemned the attack, describing it as a “flagrant violation of international law and conventions”. He said targeting Pakistan’s water infrastructure “represented a dangerous escalation and posed serious humanitarian and environmental risks.”

The 969MW project completely halted power production at 6am on May 1, 2024, after its rem­a­­ining two turbines were shut down due to deteriorating conditions in its Headrace Tunnel. The first two turbines had been shut down in early April 2024 following a reduction in tunnel pressure, just days after the project had briefly achieved full generation capacity.

Khalid Hasnain in Lahore also contributed to this report

Published in Dawn, May 9th, 2025

Opinion

Editorial

Immunity gap
Updated 26 Apr, 2026

Immunity gap

Pakistan’s Big Catch-Up campaign showed progress but also exposed the scale of gaps in routine immunisation.
Danger on repeat
26 Apr, 2026

Danger on repeat

DISASTERS have typically been framed as acts of nature. Of late, they look increasingly like tests of preparedness...
Loose lips
26 Apr, 2026

Loose lips

PAKISTANIS have by now gained something of an international reputation for their gallows humour, but it seems that...
Lebanon truce
Updated 25 Apr, 2026

Lebanon truce

THE fact that the truce between Israel and Lebanon has been extended for three weeks should be welcomed. But there...
Terrorism again
25 Apr, 2026

Terrorism again

THE elimination of 22 terrorists in an intelligence-based operation in Khyber highlights both the scale and ...
Taxing technology
25 Apr, 2026

Taxing technology

THE recent decision by the FBR’s Directorate General of Customs Valuation to increase the ‘assessed value’ of...