Pakistan moves US court to stop over $6bn fine in Reko Diq case

Published January 10, 2020
Pakistan argued that the “discounted cash flow approach”, used for awarding Tethyan, failed to properly account for certain risks and uncertainties in the project. — Abdul Razique/File
Pakistan argued that the “discounted cash flow approach”, used for awarding Tethyan, failed to properly account for certain risks and uncertainties in the project. — Abdul Razique/File

WASHINGTON: Pakistan has asked a US federal court to pause an Australian copper company’s bid to enforce a $6 billion arbitral award while it looks to have the award nixed, reports Law360, a New York-based legal publication.

The company — Tethyan Copper Co. Pty Ltd — won the award last summer following a dispute over the rejected Reko Diq mining project in Balochistan.

Pakistan argued in a federal court in Washington that the enforcement could have “devastating consequences for its political and economic stability”, said the author, Caroline Simson.

In a brief submitted in the court on Friday, Pakistan argued that Tethyan “shouldn’t be allowed to proceed with the litigation while it looks to annul the award based on “numerous substantive and procedural errors”.

Australian firm won the award last summer following dispute over the Balochistan mining project

The report noted that the award is the second largest ever to be issued by the International Centre for Settlement of Investment Disputes (ICSID) and equals 2 per cent of Pakistan’s annual gross domestic product and 40 per cent of its total liquid foreign reserves.

ICSID is an international arbitration institution established in 1966 for legal dispute resolution and conciliation between international investors and is part of and funded by the World Bank Group, headquartered in Washington.

Pakistan said in the brief that its economy was already facing “significant challenges and weaknesses” and that enforcing the award would effectively negate a $6 billion loan it received from the International Monetary Fund last year to stabilise its government and economy.

Pakistan also pointed out that ICSID’s secretary general provisionally stayed enforcement of the award after registering the annulment bid in November, adding that the benefits of pausing the litigation are “overwhelming”.

“[A] stay not only avoids the possibility of conflicting results between this court’s determination of enforcement and the ICSID’s determination to annul the award [...] but it also eliminates the time and expense associated with an appeal and any subsequent litigation,” Pakistan argued.

The brief claimed that the tribunal wrongly disregarded international law limiting the amount of damages available for lost profits and that it relied on a novel damages calculation method “without authorisation or explanation” that resulted in a number billions of dollars higher than a traditional model would, Law360 reported.

Pakistan argued that the “discounted cash flow approach”, used for awarding Tethyan, failed to properly account for certain risks and uncertainties in the project.

Also, the calculated damages were based on a projected 56-year operating period for the mine even though no lease or permits for the project were ever issued by Pakistani authorities, the brief added.

Pakistan informed ICSID that the proposed project was based on agreements that were invalid under Pakistani law and, therefore, Tethyan Copper couldn’t seek any damages.

Attorneys for the parties could not immediately be reached for comment on Monday.

The Chilean copper miner Antofagasta plc won the award last July in arbitration that arose out of Pakistan’s 2011 denial of a mining lease for the Reko Diq project.

Published in Dawn, January 10th, 2020

Opinion

Inequality virus
25 Jan 2021

Inequality virus

An Oxfam report calls for radical changes to the economic system.

Editorial

25 Jan 2021

Where the buck stops

THERE’S no getting around it: the buck stops with the prime minister. The Islamabad High Court said as much on...
25 Jan 2021

PPP’s plan?

THE PDM faces a fresh crisis as the PPP takes a conspicuously soft position on the long march. While the PDM talks ...
25 Jan 2021

Forward guidance

THE State Bank has taken the unusual step of issuing a forward guidance in its latest monetary policy statement to...
Updated 24 Jan 2021

Delayed olive branch

THE PTI government has finally mustered up sufficient political prudence to extend an olive branch to the opposition...
24 Jan 2021

Bureaucracy reform

WHILE the intention behind the endeavour may be lauded, the civil service reform package unveiled by the government...
24 Jan 2021

Minority rights

ON Thursday, the United Nations General Assembly adopted a resolution to safeguard religious sites around the world,...