KARACHI: Expressing “annoyance” over the K-Electric for slow pace of work to relocate underground utility lines along the route of the Red Line Bus Rapid Transit (BRT) project, the Sindh government on Wednesday directed the power utility to expedite its work, mainly on University Road, so that the mega project could be timely completed.

Sindh Information, Transport and Mass Transit Minister Sharjeel Inam Memon also directed the KE and other utility companies to gear up the shifting of their underground lines.

He expressed these views while chairing a meeting with the officials of utility companies including KE regarding the Red Line BRT project.

Sharjeel orders removal of encroachments within seven days; KE seeks cost of network shifting

Transport Secretary Abdul Haleem Sheikh, Karachi Commissioner Muhammad Iqbal Memon, TransKarachi chief executive Wasif Ijlal, representatives of KE, Pakistan Telecommunication Company Limited, Sui Southern Gas Company and others attended the meeting.

“KE should fulfil its obligations of relocation of its installations in time so that this project of public interest could be completed on time,” said the minister.

“Red Line is an important public project and any delay in its completion due to the KE will not be tolerated,” he warned.

The minister directed the transport secretary, commissioner and chief of TransKarachi, which is the executing agency of the project, to convene a meeting with the chief executive officer of the KE to resolve the issue of transfer and relocation of line.

Minister Memon also ordered the Karachi administration to remove all encroachments along the Red Line corridor within seven days.

He said that the transport department was working day and night for the timely completion of public transport projects in Karachi.

Currently, traffic jams especially on main University Road have become a routine feature due to construction work of the Red Line project. Motorists and commuters faced hardship and agony on a daily basis while passing through University Road.

Apparently, the minister was also aware of such complaints. He directed the project executing agency to make alternative routes on the Red Line project in a better way so that citizens would not suffer.

Later in the evening, a KE spokesperson stated that the power utility sought from the city authorities the right-of-way permissions and cost of shifting of the electricity network. “We aim to swiftly move on this as soon as requisite support is extended from the authorities concerned.”

Published in Dawn, November 24th, 2022

Opinion

Editorial

Back to politics
Updated 29 Nov, 2022

Back to politics

PDM and PTI must realise that neither will get what they want if they keep fighting bitterly at every turn.
Election delay
29 Nov, 2022

Election delay

OF recent, leaders from the ruling PML-N have been dropping hints about a possible delay in general elections after...
Sugar woes
29 Nov, 2022

Sugar woes

IT’S that time of year again when cane growers get anxious over the delay in the commencement of the new sugar...
1971 in retrospect
Updated 28 Nov, 2022

1971 in retrospect

The point of no return came when the military launched Operation Searchlight in March 1971.
Gender-based violence
28 Nov, 2022

Gender-based violence

IT is a war without boundaries and seemingly without end. A UN report on femicide released on Nov 25, the...
Battle against dacoits
28 Nov, 2022

Battle against dacoits

THE Punjab police is clearly fighting a formidable, and so far losing, battle against the criminal gangs based in ...