ISLAMABAD: Pakistan on Friday inked a loan and project agreement worth $248 million with Asian Development Bank (ADB) for power transmission enhancement investment programme.

The project is expected to be completed by the end of 2016.

The power transmission tranche-4 aims to improve energy supply and security by reducing transmission infrastructure bottlenecks and transmission losses and expanding the national transmission grid by connecting generation sources and load centers.

The transmission system is currently unable to cope with existing demand in some areas at peak times. There are voltage control issues and a high risk of instability under certain outage conditions.

Thus, the major aim of the project is enhancement in the capacity of the transmission system by rehabilitation, extension, augmentation and expansion of existing 500 kV and 220 kV network of NTDC, to meet the growing power demand in the country.

Muhammad Saleem Sethi, Secretary Economic Affairs Division (EAD) and Werner E. Liepach, Country Director ADB signed the Loan Agreement here on Friday.

Also read: ADB approves $400mn loan to boost Pakistan's energy sector

The Asian Development Bank has been providing a multi-tranche financing facility (MFF) amounting to $800 million for Power Transmission Enhancement Investment Program since 2006.

The investment program has supported the rehabilitation, augmentation and expansion of the transmission substations, transmission lines of 220 kv and above installation of static var compensator (SVC) equipments.

Tranche-4 is the last tranche of transmission MFF under which four new grid stations of 220 kv would be constructed in D I Khan, Nowshera, Lalian and Chakdara. A new transmission line of 500 kv would also be constructed for dispersal of power from 747 MW Power Plant at Guddu.

Secretary EAD Sethi appreciated ADB’s investments for the Jamshoro Coal Power Project, Budgetary Support Program for energy sector and upcoming Multi-tranche Financing Facility (MFF) for the Smart Metering System amounting to $ 990 million.

Werner E. Liepach, on the occasion, reaffirmed ADB’s support and cooperation for development projects in Pakistan.

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Restructuring plans
Updated 10 Nov, 2026

Restructuring plans

It would be a much wiser move, politically speaking, to take up any debate on administrative restructuring again after the next general election.
Extreme heat
Updated 10 Nov, 2026

Extreme heat

Climate adaptation is yet to find a place in our agricultural policies.
Israel power struggle
10 Nov, 2026

Israel power struggle

A POWER struggle is emerging after last month’s elections in Israel resulted in no party securing the requisite...
Antalya agenda
Updated 09 Nov, 2026

Antalya agenda

For Pakistan, the priority should be to secure easier access to climate funds, more grants rather than debt-creating loans, and clear deadlines for financial contributions.
Beyond viewership
09 Nov, 2026

Beyond viewership

PAKISTAN has an enormous appetite for online content. According to the Pakistan Telecommunication Authority, it...
Rabid Modi
Updated 09 Nov, 2026

Rabid Modi

Modi’s silence throughout his reign of fear shows his endorsement of hate.