Senate panel voices alarm over delays in Wapda projects

Published
0
Senator Syed Waqar Mehdi chairs Senate Sub-Committee of Standing Committee on Tuesday, June 21. —Photo courtesy @SenatePakistan/X
Senator Syed Waqar Mehdi chairs Senate Sub-Committee of Standing Committee on Tuesday, June 21. —Photo courtesy @SenatePakistan/X

ISLAMABAD: A sub-committee of the Senate Standing Committee on Economic Affairs has expressed serious concern over delays in Wapda’s hydropower projects and directed authorities to fix responsibility and submit details of the financial burden caused by cost overruns.

The meeting, chaired by Senator Syed Waqar Mehdi, was attended by Senator Haji Hidayatullah Khan, Senator Rubina Khalid and senior officials of federal and provincial departments.

The panel reviewed progress, issues, reasons for delays, cost escalations and utilisation of funds for Wapda’s ongoing projects in Khyber Pakhtunkhwa and Sindh. Projects in Punjab and Balochistan had been reviewed in the previous meeting.

Officials of the Ministry of Water Resources and Wapda briefed the committee that the project was being financed through the World Bank, foreign and local commercial loans, and Wapda’s equity. They attributed delays to land acquisition issues from 2015 to 2019, the Covid-19 pandemic in 2020-21, security incidents from 2022-24, and subsequent multiple design changes.

Senator Mehdi expressed grave concern over the prolonged delay, noting that despite repeated letters to the provincial government, the project remained stalled for five years, leading to a significant increase in cost and a heavy burden on the national exchequer. “Twelve years have passed since the project was launched, but its completion date is still not clear,” he said.

Officials said about 54 per cent of the work on Mohmand Dam had been completed. They said delays in land acquisition and design changes made to ensure dam safety had pushed the completion date to June 2028. The convener questioned why the design was repeatedly changed despite hiring consultants. “Such changes not only delay projects but also put additional financial burden on government resources,” he said.

Published in Dawn, July 22nd, 2026

Opinion

Editorial

Perilous misstep
Updated 12 Oct, 2026

Perilous misstep

If the authorities felt terrorism was increasing in some tribal districts and adjoining areas, they could have limited themselves to imposing a targeted emergency under Article 232.
Import fraud
12 Oct, 2026

Import fraud

THE under-invoicing of imports from China is not an allegation. It is an open secret in Pakistan’s markets — one...
Paralysed prisons
12 Oct, 2026

Paralysed prisons

PAKISTAN’S overcrowded jails distort the intention of imprisonment — rehabilitation, education, and occupational...
Parliament’s place
Updated 11 Oct, 2026

Parliament’s place

In 2015, the parliament had decided to “maintain neutrality in the Yemen conflict so as to be able to play a proactive diplomatic role to end the crisis”.
Disturbing the peace
11 Oct, 2026

Disturbing the peace

THIS year’s Nobel Peace Prize is well-earned. The winner, South African jurist Dr Navi Pillay, has had an...