Govt ordered to stop using Gas Infrastructure Development Cess funds for arbitration costs

Published
0

ISLAMABAD: The Public Accounts Committee (PAC) on Tuesday directed the government to cease using funds from the Gas Infrastructure Development Cess (GIDC) to cover arbitration costs.

The directive came after PAC discovered that funds meant for key gas infrastructure projects — including the Iran-Pakistan (IP) Pipeline, the Turkmenistan-Afghan­istan-Pakistan-India (TAPI) Pipeline and LNG-related initiatives — were being diverted to legal and court expenditures instead.

The committee was informed that the government had spent Rs955 million on the TAPI project and also covered arbitration costs with Iran using GIDC funds.

The members expressed concern over the slow progress of gas infrastructure projects, which has led to the accumulation of Rs350 billion in unutilised GIDC funds.

The Auditor General’s office reported that the federal government had only utilised Rs3.7bn for operational expenses of Inter State Gas System (ISGS) and repayment of its loan from Government Holdings Private Limited (GHPL).

MNA Hina Rabbani Khar suggested that the government redirect the funds to green energy or projects closer to the objective.

PAC Chairman Junaid Akbar Khan gave Petroleum Division Secretary Momin Agha one month to present alternative plans for the IP and TAPI projects.

However, Mr Agha reque­sted an in-camera briefing, citing the sensitivity of the projects.

His request was denied after PPP MNA Naveed Qamar argued that these projects were already public knowledge.

The PAC also summoned the NAB chairman and the FIA DG for a briefing on Cnergyico Pk, formerly known as Byco Petroleum, which has defaulted on Rs70bn in payments to the government.

The matter came up during a discussion on an objection raised by the Audit Depa­rtment over the non-payment of petroleum levy and late payment surcharge (LPS) on the sale of petroleum, oil and lubricants (POL), resulting in a Rs14bn loss to the government.

The committee also flagged the non-realisation of Rs33.9bn in Gas Development Surcharge (GDS), which had benefited private fertiliser and power companies that failed to make the required payments.

Published in Dawn, February 19th, 2025

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Reviewing ties
Updated 06 Nov, 2026

Reviewing ties

With the Democrats clawing back power in Congress, changes in America’s approach to global engagement are likely to occur.
Genuine engagement
06 Nov, 2026

Genuine engagement

THE PTI-led opposition alliance TTAP appears to have finally brought an initially reluctant Maulana Fazlur Rahman on...
Human bondage
Updated 06 Nov, 2026

Human bondage

Law enforcement and political quarters are notorious for protecting the perpetrators, instead of ensuring legal implementation. Systemic coercion will keep Pakistan from becoming a humane state.
Blue wave
Updated 05 Nov, 2026

Blue wave

While Trump does not usually learn from his errors, perhaps seeing the response of the American voters he may attempt a wiser course.
New LPG policy
Updated 05 Nov, 2026

New LPG policy

If the policy is enforced effectively, it could potentially help end shortages and slash prices. But the question remains whether it will.
Polio’s other victims
05 Nov, 2026

Polio’s other victims

FOR decades, Pakistan has vowed to eradicate polio. Billions have been spent on logistics and awareness drives. Yet...