GILGIT: The Water and Power Development Authority (Wapda) has claimed that land compensation for Diamer-Bhasha Dam and household packages has been paid to those affected by the project even before dam’s construction had begun.

A spokesperson for the Diamer-Bhasha dam said Wapda had completed payment of compensation amount for 91 per cent of the re­­quired land, disbursing over Rs51 billion to the affected people.

“Legal proceedings are underway for the remaining 9pc. Compensation for buildings, markets, and infrastructure was completed in 2015. The entire process was carried out by the Diamer district administration and the Gilgit-Baltistan government,” the spokesperson added.

Besides, he said, household (Chula) package payments were made to 3,826 of the 4,102 affected families. Additionally, the verification process was ongoing through the district administration for additional applicants who submitted their claims in 2024.

However, many premises including shops and petrol pumps for which Wapda has already paid compensation have not been vacated by the occupants till date, the spokesperson said.

In response to certain allegati­o­­ns levelled by protesters in Diamer recently, the spokesperson clarified that Wapda launched several major socio-economic development and basic infrastructure projects under confidence-building measures to enhance the quality of life of locals. The CBMs include projects worth Rs78bn in the education and health sectors as well as infrastructure development.

The spokesperson said that Wapda gave preference to locals in hiring for the dam project, recruiting locals for positions up to grade 16. Many also work with project consultants and contractors. Currently, he explained, thousands of employees were from the project area.

A total of 298 people from Gilgit-Baltistan are working on the Dia­mer-Bhasha Dam (reservoir part) while 354 are employed in LA&R and se­­­curity section. In total 2,120 peo­­ple from GB are working with Wapda, consultants and contract­ors of whom 1,600 are from Diamer.

Diamer-Bhasha Dam has a gross water storage capacity of 8.1MAF to irrigate 1.23 million acres of land. Power generation capacity of the project stands at 4,500MW, with annual energy generation of 18 billion units.

Published in Dawn, February 12th, 2025

Opinion

Editorial

Khuzdar atrocity
Updated 22 May, 2025

Khuzdar atrocity

A process of reconciliation is sorely needed in the province, solely militarised response will be insufficient.
Budget and climate
22 May, 2025

Budget and climate

Govt's plan to present a climate-focused budget for the next fiscal year is a welcome paradigm shift in national economic planning.
Justice for Noor
Updated 22 May, 2025

Justice for Noor

Noor's death was the result of not just one person’s malevolence, but a preventable tragedy caused by several individuals failing to do the right thing.
Gaza’s horror
Updated 21 May, 2025

Gaza’s horror

The quickest way to stop the bloodshed would be for the US to immediately halt all military and financial aid to Israel.
Climate planning
21 May, 2025

Climate planning

ALTHOUGH the effects of climate change manifest themselves throughout the year, they seem particularly more...
Failed auction
21 May, 2025

Failed auction

THE poor response to the government’s bid to sell three redundant thermal power plants indicates the investors’...