KARACHI: The Hub Power Company Ltd (Hubco) said on Friday its joint-venture (JV) partner in a coal-based 1,320-megawatt power plant has withdrawn the encashment notice it served on Hubco’s bank last month.

The announcement removes the analysts’ earlier apprehensions that the notice — served on the bank that issued a $150 million standby letter of credit (SBLC) on behalf of Hubco — would lead to increased financial costs for the country’s largest independent power producer.

The SBLC is a guarantee through which lenders ensure that equity partners cover any cost overruns or funding shortfalls that may occur before the project completion date (PCD).

Even though the plant has been producing electricity for many years, its PCD was still pending because the lenders were waiting for the fulfilment of their last condition: the establishment of a revolving fund by the Central Power Purchasing Authority-Guarantee (CPPA-G) to help independent power producers overcome their liquidity shortfalls.

The government recently set up the revolving fund, which has eliminated the need for the JV partner, China Power Hub Generation Company Ltd (CPHGC), to call the SBLC.

Hubco and CPHGC informed investors on Friday that the SBLC has been extended on “mutually agreed terms.” They didn’t state any details.

The JV partner called the SBLC on Nov 23, which was the day the facility was going to mature. Hubco didn’t renew it, which meant its JV partner would be out of opti­ons in the case of any funding shortfalls in the future.

As for the reluctance shown by Hubco in renewing the facility, analysts referred to the fact that SBLCs constitute a liability and use up the available credit lines. That’s because the issuing bank must make immediate payment on behalf of its client — Hubco, in this case — as soon as the SBLC is called upon.

Published in Dawn, December 24th, 2022

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Makkah agreement
Updated 09 Aug, 2026

Makkah agreement

IN the midst of a gruelling war between the US and Iran — currently at a stalemate — the signing of the Makkah...
Conflicting priorities
09 Aug, 2026

Conflicting priorities

THERE is a reasonable argument that the democratic process must go on regardless of prevailing conditions; that...
FIFA controversy
09 Aug, 2026

FIFA controversy

FIFA PRESIDENT Gianni Infantino is at the centre of a storm of his own making. Even after a crisis meeting in...
Danger ahead
Updated 08 Aug, 2026

Danger ahead

PAKISTAN has already paid a heavy human price this monsoon, even as another dangerous spell approaches. NDMA figures...
Israeli impunity
08 Aug, 2026

Israeli impunity

ANY hope that Hamas’s decision to disarm would lead to a breakthrough has been dashed for one simple reason:...
Flawed investigations
Updated 08 Aug, 2026

Flawed investigations

An inaccurate record of a victim’s wounds hinders the dispensation of justice. Medical examiners in such a critical area cannot cut corners.