ISLAMABAD: Amid an eight-month delay to the Mohmand Dam completion because of flood damages, the Senate Standing Committee on Planning and Development on Thursday sought an end to public procurement rules to ensure ‘quality projects in the country instead of low-cost projects.

Presided over by Senator Atta ur Rehman, the Senate panel was informed that over $1.5 billion worth of Mohmand Dam’s structure had been damaged by recent floods, resulting in a project delay of about eight months. Officials of the Planning Division said both tunnels of the dam were marred by land sliding and some other under-construction parts of the project also got damaged.

The meeting was informed that the prime minister had appointed a five-member fact-finding committee to probe the losses to the dam. The committee comprised local and international experts in relevant fields. The team had already visited the project and would soon be submitting a report to the prime minister.

The committee was informed that once completed the dam will help regulate floods, thus mitigating the risk of flooding in low-lying areas in Charsadda, Peshawar and Nowshera districts.

During a briefing on amendments to Public Procurement Regulatory Authority (PPRA) rules, the committee was informed that rules would ensure maximum transparency and efficiency as PPRA had been continually trying to remove all unnecessary hurdles in the way of development projects.

The committee was along with the lowest bid, the new rules also required standards to be the key determining factor for the award of new contracts for development projects.

The members of the committee stressed the need for doing away with PPRA rules as the country needed quality projects instead of low-cost projects.

The committee unanimously agreed to the proposal and recommended that a meeting with the prime minister should be arranged so that further transparency and improvements are introduced in awarding contracts for various development projects.

During discussions on foreign aid for flood relief activities, the Planning Com­mission officials denied that the IMF expressed reservations about estimates of flood losses in Pakistan.

Published in Dawn, December 2nd, 2022

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Digital growth
Updated 25 Apr, 2024

Digital growth

Democratising digital development will catalyse a rapid, if not immediate, improvement in human development indicators for the underserved segments of the Pakistani citizenry.
Nikah rights
25 Apr, 2024

Nikah rights

THE Supreme Court recently delivered a judgement championing the rights of women within a marriage. The ruling...
Campus crackdowns
25 Apr, 2024

Campus crackdowns

WHILE most Western governments have either been gladly facilitating Israel’s genocidal war in Gaza, or meekly...
Ties with Tehran
Updated 24 Apr, 2024

Ties with Tehran

Tomorrow, if ties between Washington and Beijing nosedive, and the US asks Pakistan to reconsider CPEC, will we comply?
Working together
24 Apr, 2024

Working together

PAKISTAN’S democracy seems adrift, and no one understands this better than our politicians. The system has gone...
Farmers’ anxiety
24 Apr, 2024

Farmers’ anxiety

WHEAT prices in Punjab have plummeted far below the minimum support price owing to a bumper harvest, reckless...