KARACHI: The groundbreaking ceremony for the Storm Water Drain project, a system that would keep Defence Housing Authority (DHA) afloat in any heavy monsoon season took place at the Farhan Shaheed Park in DHA Phase-8 here on Friday.

According to a DHA spokesperson, after the heavy rains of 2020, it was realised that the solution to the problem of flooding had to be a storm water drain through which the rainwater can be channeled out to the sea.

“Earlier, when the drains were built in 2009, only their initial phase could be completed. Work started on the second phase after the heavy rains of 2020. We started the work by bringing in the army survey engineers for a hydro-graphic profile of DHA, which showed us the high and the low-lying areas here. This was followed by DHA’s hiring the consultants who could design the drains. For this DHA brought in Zeeruk International Pvt Ltd, who readied a design in six to seven months,” the spokesperson informed.

“To have that design validated, DHA brought in a third-party, National Engineering Services Pakistan [NESPAK], and their observations were then rectified by Zeeruk. Some NED University observations about the design were also settled and the final design was prepared using best engineering practices while keeping in view Karachi’s 100-year rain records. It will be four-times the capacity of the former DHA drains,” the spokesperson added.

“The design caters to all scenarios such as high tide and the Mahmoodabad drains that receive the entire city’s drainage. The contact for the construction has been awarded to the National Logistics Cell [NLC] who are expected to complete work within 15 months.

“The design is of a 74km long drains with 18km of main drains along with interceptors and connectors that will all be under the roads with their water collectors by the side of the roads,” he said.

Published in Dawn, September 17th, 2022

Opinion

Editorial

Immunity gap
Updated 26 Apr, 2026

Immunity gap

Pakistan’s Big Catch-Up campaign showed progress but also exposed the scale of gaps in routine immunisation.
Danger on repeat
26 Apr, 2026

Danger on repeat

DISASTERS have typically been framed as acts of nature. Of late, they look increasingly like tests of preparedness...
Loose lips
26 Apr, 2026

Loose lips

PAKISTANIS have by now gained something of an international reputation for their gallows humour, but it seems that...
Lebanon truce
Updated 25 Apr, 2026

Lebanon truce

THE fact that the truce between Israel and Lebanon has been extended for three weeks should be welcomed. But there...
Terrorism again
25 Apr, 2026

Terrorism again

THE elimination of 22 terrorists in an intelligence-based operation in Khyber highlights both the scale and ...
Taxing technology
25 Apr, 2026

Taxing technology

THE recent decision by the FBR’s Directorate General of Customs Valuation to increase the ‘assessed value’ of...