Faults detected in two major grid stations in Punjab

Published
1

LAHORE: In yet another case of substandard material and equipment use, a National Transmission and Despatch Company (NTDC) team has found several discrepancies in the construction of two megaprojects, but the company’s management is reluctant to act, Dawn has learnt.

An official source told Dawn that the team visited two grid stations — a 500- kilovolt station in Rahim Yar Khan and a 220kV station in Lal Sohanra (Bahawalpur district) completed a few years ago — and found issues like substandard construction material, faulty circuit breakers, the absence of an oscillograph system, transformers in bad condition, etc.

“But such serious issues are not being taken up properly by the NTDC management,” the official said.

NTDC’s acting managing director declined to comment despite efforts to seek his version through phone calls, messages and email.

NTDC management yet to act over discrepancies, says official

According to a report shared with the NTDC’s asset management unit (north) last week, the team inspected the Rahim Yar Khan grid on Feb 9 and found serious negligence on the part of the contractor under the supervision of the company’s Extra High Voltage-II department and the consultants.

The same situation was earlier communicated to the higher officials concerned through a series of correspondences, but no prompt action was taken even after energising the grid on Feb 3, 2018.

During the Rahim Yar Khan visit, the team found a boundary wall of the grid station in deteriorated condition; increased contact resistance of circuit breaker, which keeps rising with the passage of time, affecting the current flow and may lead to tripping; and faulty design or erection of circuit breakers and isolators, causing severe vibration that may damage the pole and nearby equipment at any time.

The team found that the oscillograph system — an instrument used to indicate and record time-varying electrical quantities, such as current and voltage — had yet to be installed; use of substandard material in the civil works of a residential colony and rest houses; the non-provision of appr­oved schematic diagrams of protection and control panels, which are essential to ens­ure the quality of equipment and the non-functioning of event and fault recorders.

While visiting the Lal Sohanra grid station, the team found the foundation of the only single power transformer in deteriorated condition, substandard T&P equipment and other issues similar to the Rahim Yar Khan grid. The team recommended blacklisting of the contractors and action against consultants.

It was an official visit headed by senior officials in view of extensive correspondence made among the NTDC departments on various issues related to these megaprojects. “As many as 39 letters and reminders (15 regarding Rahim Yar Khan and 24 on the Lal Sohanra station) were written on the discrepancies emerged in these grid stations since their completion in 2018,” an official said. “But unfortunately, neither any inquiry was ordered nor someone from the NTDC office even bothered to visit these projects and take steps to rectify the issues.”

Published in Dawn, February 21st, 2022

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Kashmir unresolved
Updated 30 Sep, 2026

Kashmir unresolved

The just solution lies in India addressing the issue through a trilateral dialogue involving the legitimate representatives of the Kashmiri people and Pakistan.
Water shortage
30 Sep, 2026

Water shortage

THAT the country is entering the Rabi season with an anticipated water shortage of nearly 25pc, the lowest carryover...
Young hearts
30 Sep, 2026

Young hearts

THE observance may have passed, but the message of World Heart Day should not fade with it. The occasion is a useful...
Terror and politics
Updated 29 Sep, 2026

Terror and politics

There is an urgent need to tone down the rhetoric and tackle terrorism as a collective challenge for both the affected provinces and the federation.
Watching the glaciers
29 Sep, 2026

Watching the glaciers

THE latest signs from Pakistan’s mountains are worrying. Suparco says the number of unfrozen glacial lakes it...
Dangerous agenda
29 Sep, 2026

Dangerous agenda

AS the world remains fixated on the US-Iran conflict, elsewhere in the Middle East, Israel is consolidating its grip...