LAHORE: The National Transmission and Despatch Company (NTDC) has completed and energised the 500kV Faisalabad west grid station.

“We are focusing on upgrade of our transmission network to meet the maximum demand of power during summers and Ramazan,” NTDC Managing Director Manzoor Ahmad said at the opening ceremony in Faisalabad on Tuesday.

The grid was completed with a cost of Rs9.379 billion.

“Two transformers of 750MVA and three transformers of 250MVA have been installed at the grid station. Allied transmission lines of the grid stations have also been completed and energized,” he added.

The projects will not only strengthen the transmission network of both the NTDC and Fesco but also address the issues of overloading, low voltage and forced load shedding in the Fesco region. The completion of the project will facilitate and help to meet the increasing demand for electricity of domestic, industrial, commercial and agri consumers.

Published in Dawn, February 2nd, 2022

Opinion

Editorial

Climate choices
Updated 15 Jun, 2026

Climate choices

The country is confronting increasingly volatile weather patterns with consequences for agriculture, infrastructure, public health and economic planning.
Brief opening
15 Jun, 2026

Brief opening

WE have been here before. Throughout the weekend, there was great anticipation that a tentative framework for peace...
Environmental disaster
15 Jun, 2026

Environmental disaster

IT was a heartbreaking sight. A recent news report in these pages carried a picture of a sea turtle lying half ...
Budget presser
Updated 14 Jun, 2026

Budget presser

If the FBR falters, the government will find itself in hot water sooner rather than later.
Muharram precautions
14 Jun, 2026

Muharram precautions

WITH Muharram due to start next week, the authorities have already begun annual exercises to ensure that the ...
Blood bequests
14 Jun, 2026

Blood bequests

WORLD Blood Donor Day offers a moment of “gratitude, advocacy and renewed commitment” for thalassaemia patients...