Many NHA projects come to a halt as govt fails to release funds

Published April 5, 2021
NHA contractors did not get payments for the last three months because of non-release of funds. — DawnNewsTV/File
NHA contractors did not get payments for the last three months because of non-release of funds. — DawnNewsTV/File

ISLAMABAD: Billions of rupees’ development projects of the National Highway Authority (NHA) have virtually come to a halt due to a lack of disbursement of funds under the Public Sector Development Programme (PSDP) for the third quarter of the current fiscal year.

The NHA contractors did not get payments for the last three months because of non-release of funds and as a result they adopted a policy of either go-slow or abandoned the infrastructure projects, including those being executed under the China-Pakistan Economic Corridor (CPEC).

However, Minister for Planning and Development Asad Umar said on Sunday that all CPEC-related projects were heading towards completion on a fast pace.

The projects affected are mostly situated in Khyber Pakhtunkhwa, Punjab and Balochistan.

Schemes affected are situated in KP, Punjab and Balochistan

The government allocated Rs119 billion to the NHA in 2020-21, but the ministry concerned released only 30 per cent of the funds, making it difficult for the department to complete the projects in time.

According to an official of the communication ministry, funds for the third quarter were to be released on Jan 1, but they were released in April. The relevant ministries are bound to release PSDP funds to the NHA at the beginning of all four quarters of the fiscal year.

The contractors wait for the release of funds and in case of no-release they purchase construction material on credit and sometimes halt the projects due to non-payment of dues.

The same has happened in the third quarter of the current year when contractors were not paid their dues and they stopped work on the projects.

Major NHA development projects affected due to non-release of funds by the government include Package-6 Rehabilitation of National Highway & Bridges, Fazilpur; D.I. Khan Lot-3 Ramak-D.I. Khan; Construction of Hakla on M-I to Yarik; D.I. Khan Motorway (CPEC) (Rehmani Khel to Kot Balian), Package-2B; Construction of Hakla on M-I to Yarik D.I. Khan Motorway (CPEC), Yarak-Rahmani Khel, Package-I; Dualisation of Old Bannu Road (Gaandi Chowk to Sarai Naurang), Package-3; Dualisation of Old Bannu Road (Khurram to Krapa), Package-2; Dualisation of Old Bannu Road (Domail to Khurram), Package-1; Peshawar Northern Bypass, Packages-2 and 3; Lowari Tunnel, South Access Road, N-45; Lowari Tunnel, North Access Road, N-45; Construction of Khuzdar-Shadadkot Section of Gwadar, Ratodero Road, M-8 Section-IV, Package-III; Construction of black top road Yakmach-Kharan via Dostain Wad Khurmaqai Section-IV; Construction of Hakla on M-I to Yarik D.I. Khan Motorway (CPEC) (Pindi Gheb to Hakla), Packages I, II, III, IV and V; Lahore Eastern Bypass, Package-II; Construction of infrastructure and allied work for Metro Bus Services (Peshawar Morr-Golra Morr), packages-I and II; Dualisation of N-55, Petaro-Sehwan Section, Package-IA; and Dualisation of remaining portion of Sukkur Bypass.

When contacted, a senior official of the NHA, who did not want to be named, told Dawn that the planning division was responsible for the delay in release of funds. He, however, said the finance ministry had released the funds for the third quarter and the NHA would get them on Monday.

Published in Dawn, April 5th, 2021

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Rigging claims
Updated 04 May, 2024

Rigging claims

The PTI’s allegations are not new; most elections in Pakistan have been controversial, and it is almost a given that results will be challenged by the losing side.
Gaza’s wasteland
04 May, 2024

Gaza’s wasteland

SINCE the start of hostilities on Oct 7, Israel has put in ceaseless efforts to depopulate Gaza, and make the Strip...
Housing scams
04 May, 2024

Housing scams

THE story of illegal housing schemes in Punjab is the story of greed, corruption and plunder. Major players in these...
Under siege
Updated 03 May, 2024

Under siege

Whether through direct censorship, withholding advertising, harassment or violence, the press in Pakistan navigates a hazardous terrain.
Meddlesome ways
03 May, 2024

Meddlesome ways

AFTER this week’s proceedings in the so-called ‘meddling case’, it appears that the majority of judges...
Mass transit mess
03 May, 2024

Mass transit mess

THAT Karachi — one of the world’s largest megacities — does not have a mass transit system worth the name is ...