Neelum Jhelum project attains maximum generation capacity

Published March 30, 2019
All four units have started running on full load of 242.25 megawatt each. — Kohi Marri/ Dawn File
All four units have started running on full load of 242.25 megawatt each. — Kohi Marri/ Dawn File

LAHORE: As water flows increase with the onset of summer, the Neelum Jhelum hydropower project (NJHP) touched its maximum generation capacity of 969 megawatt once again on Friday. All four units have started running on full load (installed capacity) of 242.25 megawatt each.

The project had started operation with the commissioning of its first unit on April 13 last year. A phased commissioning of the three other units was completed by Aug 14, when the project generated electricity to its maximum capacity (969MW).

However, power generation came down because of low water flows during the winter.

“Since its commissioning in April 2018, the NJHP has so far injected over 2.1 billion units (kWh) into the national grid,” according to a press release of the Water and Power Development Authority.

The project, constructed on Neelum river in Azad Jammu and Kashmir, has a dam at Nauseri, an underground waterway system consisting of 52-km-long tunnels, and an underground powerhouse at Chattar Kalas.

“The project provides about 4.6 billion units of electricity to the national grid every year and significantly contributes to meet the electricity requirements of the country,” the press release said.

The project’s power house was shut down on Jan 5 in order to carry out an inspection — a contractual obligation. The four units remained closed for 29 days till Feb 2.

Before going into full operation with four power generating units, the project faced quite a few hiccups. In May last year, the commercial operation of its fourth unit, which was put on a trial run the previous month, was put off for four months after experts identified some technical problems in the machine during tests and sought replacement of some parts.

Although this unit injected more than 1.3 million units of electricity into the national grid during its trial run, it exceeded the specifications, leaving the consultants with no option but to replace its “labyrinth” and “lower sleeve” with new ones for a trouble-free operation. The contractor placed the order with the manufacturer, Harbin China.

In the same month (May), the first unit started providing electricity to the national grid. The second also underwent mechanical run tests in May.

Published in Dawn, March 30th, 2019

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Business concerns
Updated 26 Apr, 2024

Business concerns

There is no doubt that these issues are impeding a positive business clime, which is required to boost private investment and economic growth.
Musical chairs
26 Apr, 2024

Musical chairs

THE petitioners are quite helpless. Yet again, they are being expected to wait while the bench supposed to hear...
Global arms race
26 Apr, 2024

Global arms race

THE figure is staggering. According to the annual report of Sweden-based think tank Stockholm International Peace...
Digital growth
Updated 25 Apr, 2024

Digital growth

Democratising digital development will catalyse a rapid, if not immediate, improvement in human development indicators for the underserved segments of the Pakistani citizenry.
Nikah rights
25 Apr, 2024

Nikah rights

THE Supreme Court recently delivered a judgement championing the rights of women within a marriage. The ruling...
Campus crackdowns
25 Apr, 2024

Campus crackdowns

WHILE most Western governments have either been gladly facilitating Israel’s genocidal war in Gaza, or meekly...