Thar coal plant begins pumping power into national grid

Published March 19, 2019
Engro expects its power generation and coal mining projects to total $1.6bn in foreign exchange savings a year. ─ Photo courtesy SECMC Twitter
Engro expects its power generation and coal mining projects to total $1.6bn in foreign exchange savings a year. ─ Photo courtesy SECMC Twitter

Engro Powergen Thar Limited's (EPTL) lignite coal power plant in Thar has started pumping 330MW of electricity generated by domestic coal into the national grid.

The first of two 330MW units of the 660MW project located in Thar Block II was tested and energised on Monday, a press release issued by the company stated.

EPTL CEO Ahsan Zafar Syed told Reuters by telephone that the company is running the plant on 100 per cent local coal. The second 330MW unit will be connected to the national grid in April, he added.

Together, the mining and power projects managed by Engro are expected to rack up a total of $1.6 billion in foreign exchange savings a year since power will be produced using indigenous coal, the press release stated.

Construction on the country's first 660MW power plant, an early harvest China-Pakistan Economic Corridor project, commenced in April 2016. It was to begin generating 660MW of power by December 2018.

The EPTL power plant will utilise 3.8MTPA of coal supplied by Sindh Engro Coal Mining Company (SECMC) as both projects achieve their commercial operations date by June 2019.

Engro claims that once the projects are running, they will rake up an average of $1.6 billion in yearly foreign exchange savings. Post-COD, the plant is expected to transmit 660MW of electricity through a 282-km long 500 kV double circuit quad-bundle transmission line from EPTL plant to Matiari.

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Iran stalemate
Updated 02 May, 2026

Iran stalemate

THE US and Iran are currently somewhere between war and peace. While a tenuous ceasefire — extended largely due to...
Tax shortfall
02 May, 2026

Tax shortfall

THE Rs684bn shortfall in tax collection during the first 10 months of the fiscal year is a continuation of a...
Teaching inclusion
02 May, 2026

Teaching inclusion

DISCRIMINATORY and exclusionary content in Punjab’s textbooks has been flagged in Inclusive Education for a United...
Water vision
01 May, 2026

Water vision

WATER insecurity in Pakistan has been building up for decades as per capita water availability has declined from...
Vaccine policy
01 May, 2026

Vaccine policy

PAKISTAN has finally approved its first National Vaccine Policy; a step the health ministry has rightly described as...
Labour rights
Updated 01 May, 2026

Labour rights

THE annual observance of May Day should move beyond statements about the state’s commitment to the rights of...