LAHORE: The National Trans­mission and Despatch Company (NTDC) has allegedly failed to upgrade its 220/500kV grids and transmission system that continues to disrupt the 132/kV distribution network affecting smooth electricity supply to the consumers.

Though the NTDC had planned to upgrade the system before the summer, it couldn’t accomplish the task due to various technical and administrative reasons.

“Three transformers — each with a capacity of 450MVA — are installed at Rawat. Since this grid was facing overloading, we planned to add a 750MVA transformer before the start of summer. But, a foreign company delayed manufacturing it. However, we later received the transformer in July from the manufacturer and started civil work, which is under way and is likely to be completed along with its installation maximum by November,” an official source in the Power Division told Dawn.

“As the new transformer will share the load of the grid with the three installed already, the overloading issue will end providing relief to consumers in service areas of some major power distribution companies (Discos), including Islamabad Electric Supply Company (Iesco) and Gujranwala Electric Power Company (Gepco).”

At present, the NTDC’s 220kV and 500kV systems continue to be overloaded, affecting the power supply and distribution in the service areas of Iesco, Gepco, Faisalabad Electric Supply Company (Fesco) and Lahore Electric Supply Company (Lesco). In such a situation, the Discos are left with no option but to shed the load in rural areas or those falling within the service jurisdiction 11kV high loss feeders in a bid to save the 220/500kV system from any collapse, tripping etc.

Besides Rawat, 500kV Gatti (Faisalabad) grid station needs addition of some new transformers. It continues to be disturbed due to overloading, creating problems for Fesco directly and Lesco indirectly. At present, Gatti has three 450MVA transformers that are insufficient to absorb/bear the current load especially in peak hours.

“Here the NTDC is going to add a 600MVA transformer for which the company would require three to four months,” claimed the official. And since Gatti station’s overloading also affected Sheikhu­pura’s 500kV grid, which fed Lahore from the north, leads to disturbance on distribution system. “Therefore, after getting another transformer, Gatti will also provide relief to various service areas of Lesco,” he added.

He said the company is facing various issues right from delay in land acquisition for new projects and procurement, receipt and installation of important equipment at various hot spots of its transmission system. Although it upgraded its system, the company needs to do more for which it requires sufficient resources.

Published in Dawn, September 6th, 2018

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Business concerns
Updated 26 Apr, 2024

Business concerns

There is no doubt that these issues are impeding a positive business clime, which is required to boost private investment and economic growth.
Musical chairs
26 Apr, 2024

Musical chairs

THE petitioners are quite helpless. Yet again, they are being expected to wait while the bench supposed to hear...
Global arms race
26 Apr, 2024

Global arms race

THE figure is staggering. According to the annual report of Sweden-based think tank Stockholm International Peace...
Digital growth
Updated 25 Apr, 2024

Digital growth

Democratising digital development will catalyse a rapid, if not immediate, improvement in human development indicators for the underserved segments of the Pakistani citizenry.
Nikah rights
25 Apr, 2024

Nikah rights

THE Supreme Court recently delivered a judgement championing the rights of women within a marriage. The ruling...
Campus crackdowns
25 Apr, 2024

Campus crackdowns

WHILE most Western governments have either been gladly facilitating Israel’s genocidal war in Gaza, or meekly...