LAHORE: The board of directors (BoD) of the Lahore Electric Supply Company (Lesco) on Saturday approved revival of 25 years old project of 132kV Sheranwala Grid Station – a Gas-Insulated Substation (GIS) – directing the authorities to complete it within a short span of time.

The project was unanimously approved by all the members of the BoD in a meeting presided over by its Chairman Irfan Akram.

The Rs453 million Sheranwala Grid was envisaged in 1992 for which the then Water and Power Development Authority (Wapda) purchased private land, measuring over five kanals. In 1993, the authorities got the civil work/structure completed. However, according to the officials, the work on the station stopped after various civic agencies, including the Parks and Horticulture Authority (PHA) raised objections to it.

“One of the objections was about the land that, according to those who had raised the objections, consisted of a small piece which was insufficient for an open grid. After some years, another proposal was made, recommending a 132kV GIS grid station that can be built easily on the land purchased for this purpose,” said a senior official who was privy to the BoD meeting.

He said after inspection of Lesco in 1998, the officials resumed the work. All the necessary equipment required for a GIS was procured from a major manufacturer of the country. But later the project was again put on halt due to official bottlenecks, including change of the BoD time to time.

“For the last three to four years, Lesco’s previous BoD kept the project on halt due to reasons best known to it. However, when new BoD was constituted, the project was placed before it by the top Lesco officials,” the official explained.

“Finally on Saturday, the scheme was revived amid direction to the officials to complete it as early as possible since all objections/bottlenecks were removed,” he added.

To a question, the official said that due to the long delay, the building had turned dilapidated and it now required a huge civil work. It looks that a new building would be constructed after the demolition of the old one. Due to the delay, the project’s cost, which was about Rs409m, had gone up to Rs453m. He said the procured equipment was lying in the factory and needed revalidation by the vendors after a thorough examination.

“Had this project been completed on time, the people of Lahore would not have suffered from various constraints in the Lesco’s distribution system,” the Lesco official said.

Published in Dawn, May 21st, 2017

Opinion

Editorial

Business concerns
Updated 26 Apr, 2024

Business concerns

There is no doubt that these issues are impeding a positive business clime, which is required to boost private investment and economic growth.
Musical chairs
26 Apr, 2024

Musical chairs

THE petitioners are quite helpless. Yet again, they are being expected to wait while the bench supposed to hear...
Global arms race
26 Apr, 2024

Global arms race

THE figure is staggering. According to the annual report of Sweden-based think tank Stockholm International Peace...
Digital growth
Updated 25 Apr, 2024

Digital growth

Democratising digital development will catalyse a rapid, if not immediate, improvement in human development indicators for the underserved segments of the Pakistani citizenry.
Nikah rights
25 Apr, 2024

Nikah rights

THE Supreme Court recently delivered a judgement championing the rights of women within a marriage. The ruling...
Campus crackdowns
25 Apr, 2024

Campus crackdowns

WHILE most Western governments have either been gladly facilitating Israel’s genocidal war in Gaza, or meekly...