Water blocks metro bus test run in Islamabad

Published March 5, 2015
Rainwater has flooded the under-construction underpass at Peshawar Mor. In the other picture, a metro bus is moving on one of the completed tracks in Islamabad. — Photos by Ishaque Chaudhry
Rainwater has flooded the under-construction underpass at Peshawar Mor. In the other picture, a metro bus is moving on one of the completed tracks in Islamabad. — Photos by Ishaque Chaudhry

ISLAMABAD: Test-run of the coveted metro bus has started but unfortunately the buses could not venture very far into Islamabad on Wednesday.

A short distance from their depot, the buses found a section of their route in Islamabad blocked, not because of unfinished work but by a flooded underpass at Peshawar Mor. Though it rained a total of 63mm at the start of the week, it was enough to submerge the underpass under almost 20 feet of water.

So the shiny 68 buses imported from Turkey to run the service have to stay away from this section until the water drains out – that too naturally because neither the contractor, nor the consultant Nespak, nor the Rawalpindi Development Authority (RDA) realised that connecting the drainage system is essential in Islamabad.

Rainwater has flooded the under-construction underpass at Peshawar Mor. In the other picture, a metro bus is moving on one of the completed tracks in Islamabad. — Photos by Ishaque Chaudhry
Rainwater has flooded the under-construction underpass at Peshawar Mor. In the other picture, a metro bus is moving on one of the completed tracks in Islamabad. — Photos by Ishaque Chaudhry

In fact, during the construction of the underpass, a RDA official had assured Dawn that no water will accumulate on the bus track as “the drainage system has been laid some four feet below the ground at the point”.

Now that it has, commuters can forget the launch of the bus service in Islamabad on the speculated date of March 23.

This 4.4km long section of Package-I of MBP runs from Faizabad up to Peshawar Mor and all the four stations of the package area near completion.

“Of all the MBP sections in Islamabad, it was the only one where the test-run could take place,” said the RDA official.

Five different contracts were awarded for the Islamabad part of the MBP. Package-II covers the interchange at Peshawar Mor and there not even the 1.1 kilometre track has been completed.

Luckily, work progress is better in Package-III which covers 2.9 kilometre of track from Peshawar Mor to Centaurus.

Package-IV takes over there up to Shaheed-e-Millat Secretariat and the last package takes the metro bus to Pak-Secretariat. But work on these sections is far from finish.

Published in Dawn March 5th , 2015

On a mobile phone? Get the Dawn Mobile App: Apple Store | Google Play

Opinion

Editorial

After the deluge
Updated 16 Jun, 2024

After the deluge

There was a lack of mental fortitude in the loss against India while against US, the team lost all control and displayed a lack of cohesion and synergy.
Fugue state
16 Jun, 2024

Fugue state

WITH its founder in jail these days, it seems nearly impossible to figure out what the PTI actually wants. On one...
Sindh budget
16 Jun, 2024

Sindh budget

SINDH’S Rs3.06tr budget for the upcoming financial year is a combination of populist interventions, attempts to...
Slow start
Updated 15 Jun, 2024

Slow start

Despite high attendance, the NA managed to pass only a single money bill during this period.
Sindh lawlessness
Updated 15 Jun, 2024

Sindh lawlessness

A recently released report describes the law and order situation in Karachi as “worryingly poor”.
Punjab budget
15 Jun, 2024

Punjab budget

PUNJAB’S budget for 2024-25 provides much fodder to those who believe that the increased provincial share from the...