ATTOCK: Operation at Ghazi Barotha plant resumes

Published
0

ATTOCK, Feb 17: The Ghazi Barotha hydropower plant resumed operation on Tuesday after a 24-day closure, an official statement said. One unit has started generating power by injecting 290mw in to the national grid , an official of the Ghazi Barotha Hydro Project (GBHP) said.

He said shutdown had become necessary due to the routine inspection of power channel after its dewatering on Jan 18. The other three units will start operation soon, he added.

The statement said four units, having a total generation capacity of 1,160mw, had already been commissioned, while the testing of the last and fifth unit also commenced on Feb 16, which is expected to go into operation by the end of March, thus completing the total generation capacity of 1450mw form the GBHP.

Sources said Wapda suffered a loss of Rs2 billion due to closure of the power house.

Opinion

Editorial

Parliament’s place
11 Oct, 2026

Parliament’s place

MUCH has changed in just a little over a decade. In 2015, when the question of Pakistan’s involvement in the...
Disturbing the peace
11 Oct, 2026

Disturbing the peace

THIS year’s Nobel Peace Prize is well-earned. The winner, South African jurist Dr Navi Pillay, has had an...
A voice in care
10 Oct, 2026

A voice in care

WORLD Mental Health Day this year carries a compelling message. The theme, ‘Lived experiences heard: real voices,...
Midterm break
Updated 10 Oct, 2026

Midterm break

Both the US and Israel need to halt their destructive misadventures in the Middle East.
American barbarism
Updated 10 Oct, 2026

American barbarism

WITH the spectre of defeat in the upcoming midterm elections looming large over the Trump administration, the...