GUJRAT: A view of Kharian-Sambrial Motorway site near Dharekrri village. — Dawn
GUJRAT: A view of Kharian-Sambrial Motorway site near Dharekrri village. — Dawn

GUJRAT: The completion of Kharian-Sambrial Motorway (KSM) is facing an inordinate delay due to suspension of work for the last few months due to proposed changes in its original design.

This has been for the second time in the last couple of years that the construction work on the route has been halted. Earlier, in 2023, it’s alignment in Gujrat and Sambrial tehsils was changed due to the technical objection to the proposed site of the bridges over Chenab river by the irrigation department.

Originally designed as four-lane expressway (two-lane on each side), the KSM will now have six lanes, with Lahore-Sialkot (M-11) included.

A senior official privy to the development said that the federal ministry of communication had recently decided to add third lane to the LSM and KSM.

Work halted for land acquisition

Moreover, he said the government had also approved third lane to the Kharian-Islamabad motorway that was in the phase of land acquisition.

An official of the National Highways Authority (NHA) told Dawn the minister for communication Abdul Aleem Khan had chaired a meeting regarding the construction of motorways in Janurary where it was decided to add third to entire route of the Lahore-Sialkot-Kharian-Islamabad motorway.

He said since the new motorway would reduce distance and travel time between Lahore and Islamabad, it was likely to attract more motorists. “Keeping in view the future requirements, the ministry has taken a right and timely decision and halted work to revise cost estimates and address technical requirements,” said the official.

An official of Gujrat district land revenue department said that after the change of alignment in the Kharian-Sambrial motorway, the process of acquisition of newly- selected land had already been made by the land revenue department in collaboration with the NHA.

On the other hand, the farmers whose land has been earmarked for the acquisition of motorway project, say they have been striving hard to get the payment of their land and the matter has been put before the concerned authorities time and again but to no avail.

The affected farmers have also organsied a gathering in a village of Gujrat where they lodged a strong protest against the delay in payment and also urged the government to take notice of their long-standing issue.

The construction work on the Kharian-Sambrial motorway was started in July 2022 and as per stipulated time, it had to be completed within two years but as per the NHA sources the project might go beyond 2025.

An NHA official said that the scheme was now being revised which would definitely increase its cost due to the expansion of a lane as well as the delay.

Published in Dawn, April 10th, 2025

Opinion

Editorial

Parliament’s place
Updated 11 Oct, 2026

Parliament’s place

In 2015, the parliament had decided to “maintain neutrality in the Yemen conflict so as to be able to play a proactive diplomatic role to end the crisis”.
Disturbing the peace
11 Oct, 2026

Disturbing the peace

THIS year’s Nobel Peace Prize is well-earned. The winner, South African jurist Dr Navi Pillay, has had an...
A voice in care
10 Oct, 2026

A voice in care

WORLD Mental Health Day this year carries a compelling message. The theme, ‘Lived experiences heard: real voices,...
Midterm break
Updated 10 Oct, 2026

Midterm break

Both the US and Israel need to halt their destructive misadventures in the Middle East.
American barbarism
Updated 10 Oct, 2026

American barbarism

WITH the spectre of defeat in the upcoming midterm elections looming large over the Trump administration, the...