Bad news for University Road users as Karachi’s BRT Red Line delayed further

Published March 16, 2025
Many pedestrian bridges, like the one in the picture, over busy University Road from Nipa to Jail Chowrangi have been dismantled for the ongoing BRT Red Line project construction.—Fahim Siddiqi / White Star
Many pedestrian bridges, like the one in the picture, over busy University Road from Nipa to Jail Chowrangi have been dismantled for the ongoing BRT Red Line project construction.—Fahim Siddiqi / White Star

• CAA now wants entire scheme redesigned after 50pc of work is completed, says Sharjeel
• Announces early completion of Yellow Line

KARACHI: For Karachiites who have long been waiting for affordable and reliable transportation, there’s bad news: the completion of the Bus Rapid Transit (BRT) Red Line project may take two more years to complete thanks to the objections raised by certain stakeholders including the Civil Aviation Authority (CAA).

Hundreds of thousands of commuters who travel along University Road will continue to endure hardship during their journeys on the damaged and broken roads until at least December 2026. The multi-billion BRT project is underway for the last three years.

The bad news was shared by Senior Sindh Minister for Transport Sharjeel Inam Memon, who was visibly irked when he mentioned the demands of the CAA and told reporters that he did not believe that the BRT Red Line project could be completed by December 2026.

“There are several issues which are needed to be fixed. We had December 2026 as a target in our mind [to complete the project]. But it looks quite tough and I don’t think it will be ready by then,” he told journalists during his visit to the construction site of the BRT Yellow Line.

He blamed the utilities, including power, gas and telecom which are being operated by the government and private companies, saying that they were taking too much time to move their infrastructures.

He said the Civil Aviation Authority (CAA) had issued an NOC [no objection certificate], but now it had raised objections on one of the three components of the structures which could cause further delays in building RED Line structure.

“Drainage is one of the components. They had checked the design, discussed it with our team and then issued an NOC. Now after we have done almost 50 per cent work on that particular issue, they [CAA] have raised objections and are asking us to redesign the whole scheme. Is that some kind of joke? Things don’t move like this,” he said.

‘Yellow Line to be completed by May’

Regarding Yellow Line, Mr Memon said that the Sindh government was working tirelessly to provide maximum facilities to the public.

The Yellow Line BRT project was originally scheduled for completion in September 2025, but it will now be completed by May 2025, five months ahead of its schedule, he claimed.

The Yellow Line bus will operate from Dawood Chowrangi/Korangi 8000 Road to Shahrah-i-Quaideen up to Numaish intersection.

“CM Murad Ali Shah has issued directives to complete the tracks first at faster pace. So once these utilities’ issues are fixed, the development would happen at staggering pace,” the minister claimed.

The consultants gave a detailed briefing to the minister on the project, informing him about its progress, obstacles, and expected completion time.

Responding to a query about Green Line, he assured that fares would not be increased, but additional facilities would be introduced to provide better transport services to the public. Talking about bus procurement, Mr Memon urged the prime minister to fulfil his promise of providing 180 buses for Karachi, emphasising that it is the right of Karachi’s citizens.

He said that the prime minister should ensure better transport facilities for the people of Karachi.

Regarding special initiatives for women, he said that Pink Scooters were being provided to working women for free.

He said a Pink Taxi Service would be launched soon to offer safe and comfortable travel to women.

Published in Dawn, March 16th, 2025

Opinion

Editorial

Collective security
Updated 12 Mar, 2026

Collective security

Regional states need to sit down and talk. They must also pledge and work towards collective security.
Spectrum leap
12 Mar, 2026

Spectrum leap

THE sale of 480 MHz of fifth-generation telecom spectrum for $507m is a major milestone in Pakistan’s digital...
Toxic fallout
12 Mar, 2026

Toxic fallout

WARS can leave environmental scars that remain long after the fighting is over. The strikes on Iran’s oil...
Token austerity
Updated 11 Mar, 2026

Token austerity

The ‘austerity’ measures are a ritualistic response to public anger rather than a sincere attempt to reform state spending.
Lebanon on fire
11 Mar, 2026

Lebanon on fire

WHILE the entire Gulf region has become an active warzone, repercussions of this conflict have spread to the...
Canine crisis
11 Mar, 2026

Canine crisis

KARACHI’S stray dog crisis requires urgent attention. Feral canines can cause serious and lasting physical and...