DERA GHAZI KHAN: The canal division of the irrigation department has refused to pay consultation fee to a private consultant after its failure to prepare an up-to-the mark feasibility for the remodeling and rehabilitation of the DG Canal.

The Asian Development Bank (ADB), however, has offered to take up the task, sources told Dawn on Tuesday.

The DG Canal which originates from the right bank of the Indus river at Taunsa Barrage was constructed in 1959 with a design capacity of 8,800 cusecs to irrigate 962,434 acres of trans Indus districts of Dera Ghazi Khan and Rajanpur. The length of its network along with its branches, distributaries, minors and dub minors is about 64,448 miles.

The entire cultivated command area is located on the left side of the canal while right side of the canal is often hit by violent waters of hill torrents of Sori Lound, Vadore and Mithawan despite the construction Kachhi canal on right side which runs parallel to DG canal at a distance of about 200 feet to 600 feet.

Dawn learnt that crossing structures were made along the Kachhi canal with insufficient capacity which damaged the crossing structures on DG canal.

Floods in 2010, 2012, 2014 and 2015 badly damaged the DG canal. In 2012, the heavy monsoon in September created flooding in the mountain drains which entered Dera Ghazi Khan by breaching the DG canal.

A private consultant company was hired to prepare the feasibility report of the rehabilitation and remodeling of the canal in 2014 but it allegedly failed to prepare an appropriate report, sources alleged.

The executive engineer of the canal division told Dawn that the department had stopped working with the private consultant and halted payments on charge of not preparing the feasibility report even after the passage of seven years of the contract.

Provincial Minister for Irrigation Mohsin Khan Leghari told Dawn that the department had refused to pay the fee to the consultant for their failure to prepare the right feasibility report. The minister maintained the construction work on syphons on the canal had been initiated with consultation of Nespak.

Mr Leghari said they had initiated consultation with the ADB. He said the ADB would prepare its own feasibility report to overhaul the entire canal and its miles-long irrigation network with the estimated cost of $68 million.

He said the rehabilitation of upstream Jhelum canal and work on the Greater Thal canal phase two would also be initiated on a priority basis. He expressed his hope that the project of rehabilitation of canals would enhance their capacity and increase cultivating areas.

Published in Dawn, February 10th, 2021

Opinion

Editorial

Rigging claims
Updated 04 May, 2024

Rigging claims

The PTI’s allegations are not new; most elections in Pakistan have been controversial, and it is almost a given that results will be challenged by the losing side.
Gaza’s wasteland
04 May, 2024

Gaza’s wasteland

SINCE the start of hostilities on Oct 7, Israel has put in ceaseless efforts to depopulate Gaza, and make the Strip...
Housing scams
04 May, 2024

Housing scams

THE story of illegal housing schemes in Punjab is the story of greed, corruption and plunder. Major players in these...
Under siege
Updated 03 May, 2024

Under siege

Whether through direct censorship, withholding advertising, harassment or violence, the press in Pakistan navigates a hazardous terrain.
Meddlesome ways
03 May, 2024

Meddlesome ways

AFTER this week’s proceedings in the so-called ‘meddling case’, it appears that the majority of judges...
Mass transit mess
03 May, 2024

Mass transit mess

THAT Karachi — one of the world’s largest megacities — does not have a mass transit system worth the name is ...