CHITRAL: The site selected for the construction of University of Chitral campus in Syed Abad area near Drosh town has been termed unfeasible for such an important project as the region is hazard-prone and lacks basic infrastructure facilities.

Putting in place the required infrastructure will lead to a 27 per cent increase in the overall cost of the project, according to a report compiled by a group of geologists and civil engineers.

The field geological and technical report compiled by consultants hired by the university has noted a number of serious technical hitches, which could render the land unfeasible for construction of a mega project costing billions of rupees.

The report observed that upper reaches of the terrace across the Chitral Road were prone to geological hazards like landslides, which could damage the infrastructure in future.

Say in report area is prone to hazards, lacks basic facilities

Due to the architectural and structural design of the proposed area and the undulant ground condition the substructure design will be mostly consist of stepped and raft foundations which will increase the cost and completion period of the project, the report noted.

For the protection of the proposed building from seismic, river and hillside hazards, additional protective structures like retaining, berm and breast walls will be constructed, and for achieving the sound and leveled ground for construction, a major area of the plot will require cut and fill with appropriate material, which will also add to the cost and prolong the duration of the construction activity.

An existing public playground in the middle of the plot and a local community graveyard on the south side will seriously affect the geometry of the proposed project’s architectural design, the report pointed out.

It said that of the total 166 kanals of land about 40 kanals consisting of a steep slope towards Chitral River were unusable, thus reducing the total land for the project to 126 kanals for leveling.

The report further mentioned that the 132KV transmission line towers of Golen Gol hydropower project passing through the plot will be a constant hindrance for the current and future development of the project.

The report also noted unavailability of Internet, electricity and water in the area, which will need huge investments to be developed.

The report also pointed out that the anterior side of the plot towards the roadside was a private property of the people, and the southern side of the plot was subject to erosion by the Chitral River.

The report further observed that since the area was at a distance of 26 kilometres from the Chitral city a majority of the students would have to travel more than 52 kilometres daily to and from the university.

Published in Dawn, December 3rd, 2020

Opinion

Editorial

Sustainable path?
Updated 13 Jun, 2026

Sustainable path?

The FY27 budget is the first clear signal that the government is ready to transition from stabilisation to growth.
Prioritising education
13 Jun, 2026

Prioritising education

THOUGH the improvement in the country’s literacy rate may be slight, as highlighted by the Economic Survey, it ...
Poverty’s rise
13 Jun, 2026

Poverty’s rise

AS attention turns to the government’s plans for the coming fiscal year, one set of figures deserves particular...
A difficult story
Updated 12 Jun, 2026

A difficult story

Unless productivity becomes the dominant target of economic policy, Pakistan will continue to oscillate between crises and fragile recovery.
Rough waters
12 Jun, 2026

Rough waters

AMONGST the key potential triggers for fresh conflict in South Asia is water. The Indian state is behaving in an...
Politicised football
12 Jun, 2026

Politicised football

ALMOST three-and-half years since Lionel Messi led Argentina to FIFA World Cup glory, the latest edition of...