SC orders completion of Orange Line Metro Train project by May 20

Published April 19, 2019
The Supreme Court on Friday ordered three construction companies involved in the Lahore Orange Line Metro Train Project to submit guarantees of Rs10 million each, warning them that if the project wasn't completed by May 20, the court take possession of their guarantees. — File
The Supreme Court on Friday ordered three construction companies involved in the Lahore Orange Line Metro Train Project to submit guarantees of Rs10 million each, warning them that if the project wasn't completed by May 20, the court take possession of their guarantees. — File

The Supreme Court on Friday ordered three construction companies involved in the Lahore Orange Line Metro Train Project to submit guarantees of Rs10 million each, warning them that if the project wasn't completed by May 20, the court take possession of their guarantees.

A two-member bench of the apex court headed by Justice Gulzar Ahmed expressed displeasure over the delay in the project while hearing a case regarding the completion of the project.

During the hearing, Justice Ahmed remarked that if contractors don't work, they should be picked up and thrown away or put in jail.

Read: Why the Orange Line Metro Train in Lahore is highly controversial

The court also expressed displeasure with project director Fazal Haleem. Justice Ahmed remarked that the project director was being blackmailed by construction companies which is why the work had been delayed.

The apex court said that Justice retired Jamshed or Justice Abdul Sattar Asghar should be made the head of the technical committee on the project.

They added that if the current head, Justice Zahid Hussain, wanted to continue in his role, the Punjab government should look into it.

While adjourning the hearing of the case for two weeks, the court ordered that quality check mechanisms be ensured for the project which was in the national interest.

Opinion

Editorial

IMF’s unease
Updated 24 May, 2024

IMF’s unease

It is clear that the next phase of economic stabilisation will be very tough for most of the population.
Belated recognition
24 May, 2024

Belated recognition

WITH Wednesday’s announcement by three European states that they intend to recognise Palestine as a state later...
App for GBV survivors
24 May, 2024

App for GBV survivors

GENDER-based violence is caught between two worlds: one sees it as a crime, the other as ‘convention’. The ...
Energy inflation
Updated 23 May, 2024

Energy inflation

The widening gap between the haves and have-nots is already tearing apart Pakistan’s social fabric.
Culture of violence
23 May, 2024

Culture of violence

WHILE political differences are part of the democratic process, there can be no justification for such disagreements...
Flooding threats
23 May, 2024

Flooding threats

WITH temperatures in GB and KP forecasted to be four to six degrees higher than normal this week, the threat of...