LAHORE: The National Trans­mission and Despatch Company (NTDC) has allegedly failed to upgrade its 220/500kV grids and transmission system that continues to disrupt the 132/kV distribution network affecting smooth electricity supply to the consumers.

Though the NTDC had planned to upgrade the system before the summer, it couldn’t accomplish the task due to various technical and administrative reasons.

“Three transformers — each with a capacity of 450MVA — are installed at Rawat. Since this grid was facing overloading, we planned to add a 750MVA transformer before the start of summer. But, a foreign company delayed manufacturing it. However, we later received the transformer in July from the manufacturer and started civil work, which is under way and is likely to be completed along with its installation maximum by November,” an official source in the Power Division told Dawn.

“As the new transformer will share the load of the grid with the three installed already, the overloading issue will end providing relief to consumers in service areas of some major power distribution companies (Discos), including Islamabad Electric Supply Company (Iesco) and Gujranwala Electric Power Company (Gepco).”

At present, the NTDC’s 220kV and 500kV systems continue to be overloaded, affecting the power supply and distribution in the service areas of Iesco, Gepco, Faisalabad Electric Supply Company (Fesco) and Lahore Electric Supply Company (Lesco). In such a situation, the Discos are left with no option but to shed the load in rural areas or those falling within the service jurisdiction 11kV high loss feeders in a bid to save the 220/500kV system from any collapse, tripping etc.

Besides Rawat, 500kV Gatti (Faisalabad) grid station needs addition of some new transformers. It continues to be disturbed due to overloading, creating problems for Fesco directly and Lesco indirectly. At present, Gatti has three 450MVA transformers that are insufficient to absorb/bear the current load especially in peak hours.

“Here the NTDC is going to add a 600MVA transformer for which the company would require three to four months,” claimed the official. And since Gatti station’s overloading also affected Sheikhu­pura’s 500kV grid, which fed Lahore from the north, leads to disturbance on distribution system. “Therefore, after getting another transformer, Gatti will also provide relief to various service areas of Lesco,” he added.

He said the company is facing various issues right from delay in land acquisition for new projects and procurement, receipt and installation of important equipment at various hot spots of its transmission system. Although it upgraded its system, the company needs to do more for which it requires sufficient resources.

Published in Dawn, September 6th, 2018

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Under siege
Updated 03 May, 2024

Under siege

Whether through direct censorship, withholding advertising, harassment or violence, the press in Pakistan navigates a hazardous terrain.
Meddlesome ways
03 May, 2024

Meddlesome ways

AFTER this week’s proceedings in the so-called ‘meddling case’, it appears that the majority of judges...
Mass transit mess
03 May, 2024

Mass transit mess

THAT Karachi — one of the world’s largest megacities — does not have a mass transit system worth the name is ...
Punishing evaders
02 May, 2024

Punishing evaders

THE FBR’s decision to block mobile phone connections of more than half a million individuals who did not file...
Engaging Riyadh
Updated 02 May, 2024

Engaging Riyadh

It must be stressed that to pull in maximum foreign investment, a climate of domestic political stability is crucial.
Freedom to question
02 May, 2024

Freedom to question

WITH frequently suspended freedoms, increasing violence and few to speak out for the oppressed, it is unlikely that...