CHITRAL: The micro and mini hydro power projects (MMHPPs) of the energy department of the provincial government are far behind meeting their target of generating 6.275MW of electricity by the deadline of June 30 as current generation stands at only 2.325MW.

According to information gathered by Dawn under Right to Information Act, 2013, on August 2014, the Aga Khan Rural Support Programme (AKRSP) had been awarded the contract of constructing 55 MMHPPs in Chitral district at a cost of Rs1 billion which had to generate 6.275MW electricity.

The Pakhtunkhwa Energy Development Organization (Pedo), the executing agency of the project, has so far paid 62 per cent of the total cost of the contract to AKRSP, but only 37 per cent of the project has been completed. Initially, the contract was for two years which was extended for the second time last year, but its completion seems impossible this time as well, as only two months are left in the deadline of June 30.

Published in Dawn, April 19th, 2018

Opinion

Editorial

Iran stalemate
Updated 02 May, 2026

Iran stalemate

THE US and Iran are currently somewhere between war and peace. While a tenuous ceasefire — extended largely due to...
Tax shortfall
02 May, 2026

Tax shortfall

THE Rs684bn shortfall in tax collection during the first 10 months of the fiscal year is a continuation of a...
Teaching inclusion
02 May, 2026

Teaching inclusion

DISCRIMINATORY and exclusionary content in Punjab’s textbooks has been flagged in Inclusive Education for a United...
Water vision
01 May, 2026

Water vision

WATER insecurity in Pakistan has been building up for decades as per capita water availability has declined from...
Vaccine policy
01 May, 2026

Vaccine policy

PAKISTAN has finally approved its first National Vaccine Policy; a step the health ministry has rightly described as...
Labour rights
Updated 01 May, 2026

Labour rights

THE annual observance of May Day should move beyond statements about the state’s commitment to the rights of...