Minister for Water and Power Khawaja Muhammad Asif on Friday said the Sahiwal power plant has been connected to the national grid after its completion, reported Radio Pakistan.

He added that the power plant will generate 1,320 megawatts from June after its testing has been completed.

The first trial freight train also departed from Karachi and reached the coal terminal built at the Sahiwal power plant, which generates electricity using coal.

The spokesman for the Pakistan Railways said another train with coal will reach the power plant on Tuesday.

The $1.8 billion Sahiwal power plant has two units of 660MW each and would be first power plant to be run on imported coal.

The government, thereafter, imposed a ban on plants run on imported coal and stressed upon the need to use indigenous coal from Thar.

Opinion

Editorial

Courting controversy
Updated 01 Apr, 2023

Courting controversy

Pakistan cannot afford any of its top judges to be seen to be associated with one political narrative or the other.
No more freebies
01 Apr, 2023

No more freebies

PERHAPS amongst the major reasons Pakistan is fighting to maintain financial solvency today is that its rapacious...
Airports in private hands
01 Apr, 2023

Airports in private hands

THE government decision to ‘outsource’ the operations and land assets of the three main airports in Lahore,...
Sedition law
Updated 31 Mar, 2023

Sedition law

It is about time that our social contract is rewritten to reflect the primacy of the public’s right to democratic expression and dissent.
A step forward
31 Mar, 2023

A step forward

ALTHOUGH her post is temporary at the moment, Justice Musarrat Hilali has nevertheless made history by being...