Upgrading canals

Published January 23, 2017

A NUMBER of development projects with a focus on the Nara Canal of Sukkur barrage are being carried out by the Sindh Irrigation and Drainage Authority to improve water supply to farmlands though with some hiccups for the growers.

Four of the 14 main canals emanating from three provincial barrages have been handed over to the authority (SIDA) and the rest are managed by the Sindh irrigation department. The major works in Nara Canal include: construction of fall structure on upper Nara at RD550; rehabilitation of Ranto Canal; reconstruction of Old Jamrao Canal head regulator; reconstruction of lower Nara Canal head regulator; rehabilitation of Makhi Complex and remodelling of Khipro Canal etc.

On-going works in the left bank canals are being executed at a cost of Rs2,859m; Rs2,989m will be spent on the Ghotki Feeder and Rs3578m on the Mithrao Canal. Cost of development works in the lower Nara and Makhi Complex are estimated at Rs7,474m and Rs2,479m respectively.

The upgradation projects include: Ghotki Feeder of Guddu Barrage, Phulelli and Akram of Kotri Barrage and Mithrao of Nara Canal System. According to a SIDA spokesman, 30pc progress has been achieved in the left bank canals and Ghotki Feeder canal while work is a bit slow in Mithrao canal. Nara canal feeds farms right upto Sanghar and Mirpurkhas districts.


Mahmood Nawaz Shah feels that an independent assessment of all these works is necessary to know how effectively the system has really been improved and whether the water supplies have indeed been ensured


Sindh Abadgar Board President Abdul Majeed Nizamani says that projects completed by the SIDA have improved water availability to tail enders.

But some farmers complain water shortages still persist.

They say some engineering works are adversely affecting water supply to farms.

Murad Nizamani — a grower from Sanghar — points out that Nara canal is taking lesser water flows at some points, as it accumulates silt.

The SIDA has set up farmers’ participatory organisations (FOs) to manage of the canal systems. But farmers’ representative Mahmood Nawaz Shah claims that usually selection is preferred over election in the farmers’ body.

Water theft, admitted a SIDA officer, has not come to an end in SIDA controlled areas.

He, however, mentioned that in case of Khipro Canal, protests against water shortage have now died down. He also said issues in maintenance of these works are still a gray area.

A farmer-cum-member of the Left Bank Canals Area Water Board said unsettled administrative issues between irrigation department and the SIDA tended to fail the authority-run system.

Mahmood Nawaz Shah feels that an independent assessment of all these works is necessary to know how effectively the system has really been improved and whether the water supplies have indeed been ensured.

Published in Dawn, Business & Finance weekly, January 23rd, 2017

Opinion

Editorial

Rigging claims
Updated 04 May, 2024

Rigging claims

The PTI’s allegations are not new; most elections in Pakistan have been controversial, and it is almost a given that results will be challenged by the losing side.
Gaza’s wasteland
04 May, 2024

Gaza’s wasteland

SINCE the start of hostilities on Oct 7, Israel has put in ceaseless efforts to depopulate Gaza, and make the Strip...
Housing scams
04 May, 2024

Housing scams

THE story of illegal housing schemes in Punjab is the story of greed, corruption and plunder. Major players in these...
Under siege
Updated 03 May, 2024

Under siege

Whether through direct censorship, withholding advertising, harassment or violence, the press in Pakistan navigates a hazardous terrain.
Meddlesome ways
03 May, 2024

Meddlesome ways

AFTER this week’s proceedings in the so-called ‘meddling case’, it appears that the majority of judges...
Mass transit mess
03 May, 2024

Mass transit mess

THAT Karachi — one of the world’s largest megacities — does not have a mass transit system worth the name is ...