PESHAWAR: The project of computerisation of land record and establishment of service delivery centres across Khyber Pakhtunkhwa is in doldrums as only Rs427.367 million out of the estimated cost of Rs6.8 billion could be spent on the execution of the plan during the previous few years, according to sources.

They said that the utilised amount was only 6.2 per cent of the total estimated cost. The provincial revenue department had planned computerisation of land record and establishment of service delivery centres in two phases but the plan could not be executed within the schedule time due to meagre spending.

Sources said that computerisation of land record was the brainchild of the previous provincial government as a decision in that regard was taken in 2012. Initially it was planned for seven districts including Peshawar, Mardan, Abbottabad, Buner, Kohat, Bannu and Dera Ismail Khan, they said.

Sources said that estimated cost of the first phase of the project, meant for seven districts, was Rs1.245 billion that and it was scheduled to be completed in 2016-17. They said that utilisation of funds on the first phase of the project started in 2013-14.


Only 6.2 per cent of project amount utilised


With a few months left to the deadline, the revenue department has so far spent only Rs346.484 million, which is 27.8 per cent of the estimated cost of the first phase of the scheme.

“Computerisation of land record is in progress in the seven districts while the PTI-led provincial government has decided to extend it to 12 more districts of the province,” said sources.

The new districts where the plan will be implanted include Charsadda, Nowshera, Swabi, Haripur, Mansehra, Battagram, Swat, Shangla, Karak, Hangu, Lakki Marwat and Tank.

“The government has also decided to establish services delivery centres across the province for the convenience of the people and elimination of patwarkhanas where patwaris take bribe from people,” sources said. The extension of the plan to 12 more districts and establishment of services delivery centres have been described as second phase of the project.

Sources said that estimated cost of the second phase of the scheme was Rs5.561 billion and its completion time was 2017-18. However, due to meagre releases of funds, the revenue department could only spent Rs80.883 million, which was 1.454 per cent of the total allocation, they added.

Sources said that in 2014, the government amended Khyber Pakhtunkhwa Land Revenue Act, 1967 to allow computerisation of land record. Beside meagre allocation of funds, the non-cooperation of patwaris was also one of the reasons of delay in the execution of the plan, they added.

They said that patwaris took a lot of time in verification of documents related to land record, sent by the officials involved in the computerisation process. “So far only two services delivery centres including that of Peshawar and Mardan have started functioning partially,” they said.

Sources said that according to PC-I for the first phase, it was planned to establish a project management unit for the execution of the project but it couldn’t be set up during the last three years.

A senior official in the provincial revenue department, when contacted, said that newly appointed Senior Member of Revenue Afzal Latif was making efforts to execute the project.

He said that efforts were also underway to establish project management unit and remove flaws from the system.

Published in Dawn, November 22nd, 2016

Opinion

Editorial

IMF’s unease
Updated 24 May, 2024

IMF’s unease

It is clear that the next phase of economic stabilisation will be very tough for most of the population.
Belated recognition
24 May, 2024

Belated recognition

WITH Wednesday’s announcement by three European states that they intend to recognise Palestine as a state later...
App for GBV survivors
24 May, 2024

App for GBV survivors

GENDER-based violence is caught between two worlds: one sees it as a crime, the other as ‘convention’. The ...
Energy inflation
Updated 23 May, 2024

Energy inflation

The widening gap between the haves and have-nots is already tearing apart Pakistan’s social fabric.
Culture of violence
23 May, 2024

Culture of violence

WHILE political differences are part of the democratic process, there can be no justification for such disagreements...
Flooding threats
23 May, 2024

Flooding threats

WITH temperatures in GB and KP forecasted to be four to six degrees higher than normal this week, the threat of...