MULTAN: Metro Bus Project Technical Adviser Sabir Khan Sadozai says carpeting of the Metro Bus Track’s carriageway is under way.

Giving a briefing here on Sunday, he said carpeting of Bosan Road from Science College to Chungi No 9 had been completed, while carpeting of the other side of the same road is under way. It will be completed within two days.

He said the road work and patchwork between Chungi No 6 and Sabzazaar Colony had been completed and road was being prepared with asphalt.

He said 90pc carpeting work on both sides of the carriageway from Sabzazaar Colony to Bahauddin Zakariya University had been completed, while carpeting work was in its final stage from Chowk Kumharanwala to Allah Wasaya Chowk.

Published in Dawn, May 23rd, 2016

Opinion

Editorial

On press freedoms
Updated 03 May, 2026

On press freedoms

THE citizenry forgets, to its own peril, how important a free and independent media is in the preservation of their...
Inflation strain
03 May, 2026

Inflation strain

PAKISTAN’S return to double-digit inflation after 21 months signals renewed economic strain where external shocks...
Troubled waters
03 May, 2026

Troubled waters

PAKISTAN’S water crisis is often framed in terms of scarcity. Increasingly, it is also a crisis of contamination....
Iran stalemate
Updated 02 May, 2026

Iran stalemate

THE US and Iran are currently somewhere between war and peace. While a tenuous ceasefire — extended largely due to...
Tax shortfall
02 May, 2026

Tax shortfall

THE Rs684bn shortfall in tax collection during the first 10 months of the fiscal year is a continuation of a...
Teaching inclusion
02 May, 2026

Teaching inclusion

DISCRIMINATORY and exclusionary content in Punjab’s textbooks has been flagged in Inclusive Education for a United...