ISLAMABAD: The state council of the People's Republic of China granted approval for an investment of $1.2 billion in the surface mining of Thar coal and the establishment of 660 MW power projects, as part of the China-Pakistan Economic Corridor project (CPEC).

The final lending documents in this regard will be signed on December 21 in Beijing.

According to details shared on Wednesday, China's state council for financing gave final nod for establishment of 660 MW Power Plant on indigenous coal in Thar Block-II and the surface mining of 3.8 MTPA (million tonnes per annum of Thar coal.

Earlier, in October, the Chinese government had agreed to increase the financing of Thar Coal project to double the generation capacity of Thar Block-II from 660 to 1,320MW, and to add project capacity and increase the mine size from 3.8 to 6.5 million tonnes per annum as part of the priority list of CPEC projects.

In a letter addressing Secretary Ministry of Water and Power Muhammad Younus Dagha, the Chinese side confirmed the approval of financing of mega project by China's state council.

Sinosure in collaboration with Sindh Engro Mining Company are jointly undertaking Surface Mining of 3.8 MTPA and establishment of 660 MW Power Plan projects in Thar Block-II which is part of China Pakistan Economic Corridor (CPEC) projects.

According to the ministry, reaching this stage of collaboration is considered as a major achievement in shortest time.

Arrangement of finances and completion of lending documents is the most critical part in any project which signifies starting of actual work on the projects.

This project was on the government's priority list which helped it reach the advanced stage among other CPEC mega projects, after signing of CPEC energy projects agreement in November, 2014.

It is worthy to mention that due to tireless efforts of Ministry of Water and Power and NEA China, all the regulatory requirements have been completed in one year's time.

Thar Coal has remained on agenda of every government, however, practical steps have been taken by the Ministry for first time since present government focused on tapping potential to its fullest.

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Uneasy calm
Updated 25 Jun, 2025

Uneasy calm

The US needs to stop its flow of funds and arms to Israel if it really wants lasting, substantive peace in the Middle East.
Judicial extensions
25 Jun, 2025

Judicial extensions

WITH the public’s attention on the rapidly deteriorating situation in the Middle East, the Judicial Commission of...
Asia on edge
25 Jun, 2025

Asia on edge

THE World Meteorological Organisation’s State of the Climate in Asia 2024 report lays bare the continent’s...
Agriculture concerns
24 Jun, 2025

Agriculture concerns

PRIME Minister Shehbaz Sharif appears relieved that the IMF did not turn down Pakistan’s request to exempt...
OIC reaction
Updated 24 Jun, 2025

OIC reaction

The bare minimum OIC can do is to take firm action against the butchery of Palestinian people and resist regime change.
NEVs, but for whom?
24 Jun, 2025

NEVs, but for whom?

THE government’s policy gymnastics following Pakistan’s unexpectedly rapid adoption of rooftop solar have ...