ISLAMABAD: Prime Minister Nawaz Sharif has ordered two separate audits — one by an audit firm of international repute and the other by the auditor general of Pakistan – into matters relating to the 525MW Nandipur power project.

Minister for Planning and Development Ahsan Iqbal said at a news conference here on Monday that the prime minister had also ordered an inquiry to ascertain why the plant remained closed for four or six weeks after completion and fix responsibility in the event of negligence.

Also read-editorial: Nandipur fiasco

Mr Iqbal said the prime minister had also ordered that an audit firm of international repute and the auditor general of Pakistan be assigned to determine if misappropriation had taken place in the project.

He said the project had been started in 2009 when the PPP was in power and claimed that one of its ministers had kept the file in his drawer for ulterior motives for over one year.

He said the project was now a reality, its test trial complete and it was waiting to be given on operation and maintenance contract which had been delayed.

He said a judicial commission appointed by the Supreme Court and headed by a former reputed senior judge had reported Rs130 billion loss to the national kitty because of the alleged sabotage by the PPP minister. He said that the contractors had left the country and machines and material kept rusting for years at the port.

Mr Iqbal said that the PML-N government had taken upon itself to revive the project to avoid international arbitration by contractors which seemed going against Pakistan and could have earned a bad name for the country among the international community.

“It is like a thief blaming the cop,” the minister said, referring to criticism coming from the PPP over the Nandipur fiasco, adding that it was the PPP that had harmed the nation by destroying a national project.

Another cabinet member said that the adoption of high sulphur fuel oil (HSFO) for a combined cycle plant to be run on natural gas was the basic flaw in the power project because it was technically difficult to run such a big unit on the HSFO that also contained a lot of contamination when brought from Karachi to Nandipur.

Published in Dawn, September 15th, 2015

On a mobile phone? Get the Dawn Mobile App: Apple Store | Google Play

Opinion

Editorial

Rigging claims
Updated 04 May, 2024

Rigging claims

The PTI’s allegations are not new; most elections in Pakistan have been controversial, and it is almost a given that results will be challenged by the losing side.
Gaza’s wasteland
04 May, 2024

Gaza’s wasteland

SINCE the start of hostilities on Oct 7, Israel has put in ceaseless efforts to depopulate Gaza, and make the Strip...
Housing scams
04 May, 2024

Housing scams

THE story of illegal housing schemes in Punjab is the story of greed, corruption and plunder. Major players in these...
Under siege
Updated 03 May, 2024

Under siege

Whether through direct censorship, withholding advertising, harassment or violence, the press in Pakistan navigates a hazardous terrain.
Meddlesome ways
03 May, 2024

Meddlesome ways

AFTER this week’s proceedings in the so-called ‘meddling case’, it appears that the majority of judges...
Mass transit mess
03 May, 2024

Mass transit mess

THAT Karachi — one of the world’s largest megacities — does not have a mass transit system worth the name is ...