REIP fails to achieve its goal: ADB

Published
0

The ADB report pointed out that building of hygienic and environmentally acceptable slaughterhouse facilities at the premises of existing Sihala Slaughterhouse and construction of 15 public toilets were not carried out. - File photo

 

ISLAMABAD: The Asian Development Bank (ADB) said the Rawalpindi Environment Improvement Project (REIP) failed to achieve sustainable reduction in environmental degradation and operation of basic urban services.

ADB in its assessment report released on Wednesday stated that the project was closed prematurely as it was facing serious implementation delays.

Poor performance of civil works contractors, especially on sewerage and drainage contracts, was another important reason for not delivering according to the project schedule.

As a result, many works were left incomplete at the time of closure. Many of the studies, plans, surveys, maps, and capacity building activities under the institutional development component were either left incomplete or not initiated at all.

The project was estimated to cost $85.7 million, out of which ADB provided two loans worth $60 million while the Punjab government was to provide $21.4 million and the remaining $4.3 million were to be contributed jointly by Wasa and Rawal Town.

The ADB assessment report noted that at completion, only 23 per cent of the project cost -- $19.6 million -- was utilised. ADB financed $13.7 million while the government financed $5.89 million of the utilized amount. Rawal Town and Wasa did not contribute a single penny.

The project was in the second phase of the proposed three-phase plan for improving water and sanitation services in Rawalpindi.

The first phase for $72 million was approved in 1993 for the Rawalpindi Urban Water Supply and Sanitation project under which water supply was increased by 64,000 cubic meters per day with rehabilitation and extension of the water supply distribution network.

The major reasons for project failure were initial design gaps, new projects with overlapping scope initiated by the government after project approval, overall external resistance to reforms, weak consultants' capacities and implementation arrangements, and indecision regarding the scope of the project.

Except for acquisition of land, no work was undertaken on the Sewerage Treatment Plant (STP) the report stated. Similarly, the remodeling of storm water drainage and construction of new drains hit snags.

Contracts were awarded for the construction of the Asghar Mall road drain from Murree road to Nullah Lai, and remodeling of the drain at Jamia Masjid.

However, these were terminated without undertaking any work, as both sites were heavily encroached and their resettlement plans were neither updated nor implemented.

The ADB report pointed out that building of hygienic and environmentally acceptable slaughterhouse facilities at the premises of existing Sihala Slaughterhouse and construction of 15 public toilets were not carried out.

No work was undertaken for rehabilitation of the slaughterhouse because of a delay in the design of the facility by the consultant and lack of capacity of the City District Government in operating this facility.

On the positive side, the report stated that the project substantially increased the capacity of the implementing agencies to collect solid waste, without adding any sanitary landfill for safe disposal. The project reduced water wastage (leakages) and added additional water to the distribution system, but was unable to achieve a corresponding increase in the capacity of the sewage and drainage networks and wastewater treatment facilities to carry and treat the additional water, thus the reduction in the environmental degradation of the city was marginal.

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Balochistan’s wounds
16 Aug, 2026

Balochistan’s wounds

ALTHOUGH Balochistan has been experiencing varying degrees of tumult for over two decades now, currently, the...
Tax scheme
16 Aug, 2026

Tax scheme

THE Hyderabad SITE Association of Trade and Industry has formally endorsed new measures introduced to ease...
In choppy waters
16 Aug, 2026

In choppy waters

MORE than three months after Somali pirates captured an oil tanker carrying a multinational crew, including 11...
Governance test
Updated 15 Aug, 2026

Governance test

EVER since the interior minister called for smaller administrative units to improve governance, the question of new...
Sailors’ killing
15 Aug, 2026

Sailors’ killing

THE killing of at least three Pakistani sailors in an apparent Houthi attack targeting a vessel in the waters of Bab...
Lethal celebrations
15 Aug, 2026

Lethal celebrations

IT is a familiar tale. Every year, occasions for national celebration turn into fear and mourning just because some...