Luxury family suites for parliamentarians

Published
0

ISLAMABAD, Sept 27: At a time when the government has refused to fund projects of the public sector universities, it is going ahead with construction of nearly Rs3 billion luxury family suites for the parliamentarians.

Initially the cost for constructing 106 family suites was Rs3.04 billion, which was revised to Rs2.91 billion, sources told .

Ramzan Sajid, spokesman of the Capital Development Authority, said though the CDA was executing agency, the federal government was funding the project. Mr Sajid said five firms qualifying the recently held pre-qualification process would participate in the final bidding.

The multi-storey flats would be an extension of the Federal Lodges in front of the Parliament House. The spokesman said everything, including design of the project, was finalised, and soon the authority would announce the final bidding process. The construction of the suites would be completed in two to three years, he added.

According to the project details available with Dawn, Rs296.11 million would be spent on furniture and furnishing of the building that would have eight lifts to facilitate the lawmakers.

The project's cost also includes a massive Rs53.55 million under the head of consultancy and supervision charges. A Lahore-based consultants firm is looking after the project. According to the documents, the cost of the land 3.96 acres — 19157.78 sq yard — has been determined as Rs86.20 million — Rs4,500 per sq yard.

A CDA official, who did want to be named, said it was the federal government decision to construct additional family suites for the parliamentarians. “Now all eyes are on the bidding process and let's see which of the firms grab it, because all of them have moved their right connections,” said the official.

Last week teachers of all 72 government-run universities had gone on strike against the non-payment of their increased salaries and stoppage of funds for the development of higher education institutions. Moreover, after the floods, the government, which had almost stopped releasing funds under the development heads, has revised the Public Sector Development Programme (PSDP) downward for the current financial year.

Opinion

Editorial

Nuclear uncertainty
Updated 23 Oct, 2026

Nuclear uncertainty

With matters frozen in the political and diplomatic spheres, it will take military-to-military engagement to prevent miscalculation in the strategic sphere.
Auto illusion
23 Oct, 2026

Auto illusion

PAKISTAN’S draft auto policy 2026-31 is ambitious in its targets and directionless in its strategy. It promises...
Two crimes
23 Oct, 2026

Two crimes

THE senseless killing of a teenager by his employers in Multan is a crime that deserves unqualified condemnation. It...
Makkah pact clarity
Updated 22 Oct, 2026

Makkah pact clarity

Fresh aggression can kick off a firestorm that will be in no one’s control, hence it is best to abandon such reckless plans.
Common ground
Updated 22 Oct, 2026

Common ground

Regrettably, the two sides still fail to see the country’s economic, security, and governance crises as challenges that must be solved politically.
The treatment gap
22 Oct, 2026

The treatment gap

A BREAST cancer diagnosis no longer carries the bleak outlook it did a generation ago. Targeted medicines,...