KARACHI, July 13: The Karachi Water and Sewerage Board (KWSB) has offered three reasons for the delay in the completion of the much-awaited Lyari water project. KWSB managing-director Ghulam Arif said on Friday that the Lyari town nazim had requested for an extension of the pipeline from Bakra Piri to Mira Naka besides a change of route from Lyari Nadi towards Mirza Adam Khan Road.

“These changes also resulted in an increase in the overall cost and delayed the project,” he stated.

A Lyari NGO had approached the Sindh High Court against a waterline project along the Lyari River. However, the court allowed the execution of the project as planned but the pace of work had suffered due to litigation, he added.

He said that another factor was the attitude of the previous contractor who was not serious about the project and was carrying out the work at a snail’s pace besides manoeuvring in a way to get the project’s cost raised. The contract was rescinded to save the financial interests of the water utility.

Opinion

Editorial

A difficult story
Updated 12 Jun, 2026

A difficult story

Unless productivity becomes the dominant target of economic policy, Pakistan will continue to oscillate between crises and fragile recovery.
Rough waters
12 Jun, 2026

Rough waters

AMONGST the key potential triggers for fresh conflict in South Asia is water. The Indian state is behaving in an...
Politicised football
12 Jun, 2026

Politicised football

ALMOST three-and-half years since Lionel Messi led Argentina to FIFA World Cup glory, the latest edition of...
GB polls’ aftermath
Updated 11 Jun, 2026

GB polls’ aftermath

The new administration must address the region’s issues proactively.
Peace in retreat
11 Jun, 2026

Peace in retreat

THE ceasefire announced in April was supposed to create space for negotiations. Instead, it has been repeatedly...
A few good men
11 Jun, 2026

A few good men

IT was a brave move, no doubt. This Tuesday, in the land of the Afghan Taliban, a few good men decided to take a...