Mari Energies faces $19.1m International Chamber of Commerce claim

Published Updated
A file photo of a gas field. — Dawn/file
A file photo of a gas field. — Dawn/file

ISLAMABAD: Petrosin CNG, a company operating in Pakistan, has initiated proceedings before the International Chamber of Commerce (ICC), London, against Mari Energies Ltd, seeking damages of $19.1 million (approximately Rs5.357 billion), along with arbitration costs, for the alleged unlawful termination of its gas supply.

Mari Energies, one of the country’s top three oil and gas producers, has contested Petrosin’s claims and defended its decision to terminate the Gas Sales and Purchase Agreement (GSPA) because of the claimant having no valid licence.

According to court filings, Petrosin CNG contends that Mari Energies unlawfully terminated the GSPA, causing substantial commercial losses for which it seeks compensation through international arbitration.

Petrosin filed a Civil Petition for leave to appeal before the Supreme Court of Pakistan under Article 185(3) of the Constitution of the Islamic Republic of Pakistan against the judgment of Jan 1, 2026 by a single bench of the Islamabad High Court that ruled in favour of Mari, saying it validly terminated the GSPA.

Petrosin alleges unlawful termination of gas contract

Petrosin CNG (Pvt) Ltd entered into GSPA with Mari for the supply of gas from the Halini Production Field. Under the terms, the agreement was to remain in effect for as long as gas remained available from the field, provided that the buyer was not in breach of its obligations under the GSPA.

Petrosin contends that the GSPA was a binding commercial contract governed by the laws of Pakistan and contained a clear and unequivocal arbitration agreement providing for the resolution of disputes under the International Chamber of Commerce Rules of Arbitration, with the seat of arbitration in London.

Mari Energies issued a termination notice in May 2025, which Petrosin contends was unlawful and contrary to the terms of the GSPA. Petrosin initially approached the Civil Court, which, by an order in June 2025, granted interim relief preserving the status quo pending adjudication.

Thereafter, Petrosin invoked the arbitration agreement by commencing arbitration under the ICC Rules and also filed an Enforcement Petition under the Recognition and Enforcement (Arbitration Agreements and Foreign Arbitral Awards) Act 2011, seeking recognition and enforcement of the arbitration agreement, together with interim and conservatory measures pending the arbitral proceedings.

The IHC, however, dismissed the said Enforcement Petition.

The case adds to a growing list of international commercial arbitrations involving Pakistan’s energy sector.

Published in Dawn, July 15th, 2026

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Beyond declarations
Updated 15 Jul, 2026

Beyond declarations

States that fail to harness the talents of half their population limit their own growth and resilience.
A timely authority
15 Jul, 2026

A timely authority

EVERY summer now seems to bring fresh warnings from Pakistan’s northern mountains. This week was no different, ...
India voter purge
15 Jul, 2026

India voter purge

AFTER over 12 years of BJP rule, minorities in India — particularly its Muslims — face fascist thuggery at the...
Dire straits
Updated 14 Jul, 2026

Dire straits

FOR some time, the escalating confrontation between the US and Iran has been playing out round the strategically...
Ethnic targets
Updated 14 Jul, 2026

Ethnic targets

THE murder of five workers from Punjab in Mashkel is another grim reminder that ethnic violence remains a persistent...
Poverty punished
14 Jul, 2026

Poverty punished

THE challenge of illegal migrations should be viewed through a humanitarian lens. Harsh punishments for the poor...