SWABI: Representatives of the Gajju Khan Medical College Swabi have voiced concern over slow construction activities on the premises and demanded speedy work on the building.

The demand came as Dean Prof Shamsur Rehman chaired a meeting in his office regarding the GKMC building and the establishment of Gajju Khan Dental College.

The participants, including representatives of GKMC, communication and works department, consultants and contractors, discussed the delayed project and possible steps for its early completion.

They said the initial cost of the project was Rs2.6 billion but it increased as the project faced prolonged delay due to the government’s failure to release funds.

Officials of the communication and works department officials said the revised estimated expenditures were expected to be released soon.

Dean says contractor’s ‘delaying tactics’ no more acceptable

The participants decided that priority would be given to the academic block’s construction.

They said the Bacha Khan Hospital, too, faced problems as its building had been used by the college for a decade.

The officials said since its establishment in 2014, the GKMC had operated in the makeshift building of the hospital.

They said the foundation stone of the college’s own building was laid in September 2022 and the construction began soon thereafter. However, the work was later stopped several times due to shortage of funds despite the students’ urgent need to have their own building for security reasons.

The officials said the college had to rent a building outside for a boys hostel, while the girl students were accommodated inside the Bacha Khan hospital.

After the meeting, the dean, along with the project director and other officials, visited the construction site and voiced concern over the slow pace of work.

He ordered speedy construction, complaining the project has already been delayed for years. The dean warned that “more” delaying tactics of the contractor were not acceptable.

However, the contractor wondered how he could accelerate construction activities amid denial of government funding.

The participants agreed on a way forward regarding the establishment of the dental college.

Published in Dawn, March 29th, 2026

Opinion

Geopolitical shift in ME

Geopolitical shift in ME

A prolonged conflict will have far-reaching implications for regional geopolitics, sharpening the divisions among Gulf countries that are directly affected by the tensions.

Editorial

Unyielding stances
Updated 13 May, 2026

Unyielding stances

Every day that passes without clarity on how and when the war will end introduces fresh intensity to the uncertainty roiling global markets and adds to the economic turmoil the world must bear because of it.
Gwadar rising?
13 May, 2026

Gwadar rising?

COULD the Middle East conflict prove to be a boon for the Gwadar port? Islamabad’s push to position Gwadar as a...
Locked in
13 May, 2026

Locked in

THE acquittal of as many as 74 PTI activists by a Peshawar court in a case pertaining to the May 2023 violence is a...
Bannu attack
Updated 12 May, 2026

Bannu attack

The security narrative and strategy of the KP government diverges considerably from the state’s position.
Cotton crisis
12 May, 2026

Cotton crisis

PAKISTAN’S cotton economy is once again facing a crisis that exposes the country’s flawed agricultural and...
Buddhist heritage
12 May, 2026

Buddhist heritage

THE revival of Buddhist chants at the ancient Dharmarajika Stupa in Taxila after nearly 1,500 years is much more ...