CHITRAL: About 300 youths from Torkhow valley of Upper Chitral helped a contractor complete a reinforced concrete cement (RCC) bridge in Istaru village, working continuously for 12 hours.

Hussain Zareen Charwelu, a leader of the youth, told Dawn that the inordinate delay in completion of the bridge had become a big issue for the residents of Torkhow and Terich valleys as it connected the valleys with rest of the district.

He said the contractor of the communication and works department was in a fix as he required a large number of labourers to complete the bridge’s deck in one go.

Mr Charwelu said youth from three villages decided to lend help to the contractor complete work on the bridge in a single day.

Jalaluddin, a retired army official who also worked on the site, said it was a huge task as they had to fill the 200-foot-long and 10-foot-wide deck of the bridge with gravel-cement-sand mixture in a single day.

He said the bridge was a game changer for the valleys of Torkhow and Terich, adding it would take another two weeks before the traffic was restored on it.

He said heavy vehicles would also be able to come to the valleys using the bridge.

Published in Dawn, November 24th, 2021

Opinion

Editorial

A new war
Updated 01 Mar, 2026

A new war

UNLESS there is an immediate diplomatic breakthrough, the joint Israeli-American aggression against Iran launched on...
Breaking the cycle
01 Mar, 2026

Breaking the cycle

THE confrontation between Pakistan and Afghanistan has taken a dangerous turn. Attacks, retaliatory strikes and the...
Anonymous collections
01 Mar, 2026

Anonymous collections

THE widespread emergence of ‘nameless donation boxes’ soliciting charity in cities and towns across Punjab...
Afghan hostilities
Updated 28 Feb, 2026

Afghan hostilities

The need is for an immediate ceasefire and substantive negotiations, with the onus on the Taliban to rein in cross-border attacks.
Cutting taxes
28 Feb, 2026

Cutting taxes

PRIME Minister Shehbaz Sharif’s plan to cut direct taxes for businesses in the next budget acknowledges the strain...
KCR challenge
28 Feb, 2026

KCR challenge

THE Karachi Circular Railway is being discussed again. It seems that the project, or, rather, the hopes of it, are...