SSGC board recalls Exquisite back to work

Published September 4, 2021
Sui Southern Gas Company has rejected Engro Elengy Terminal upgr­ade to a bigger floating storage and regas­ification unit and instead recalled original unit — Exquisite — back to work. — Dawn/File
Sui Southern Gas Company has rejected Engro Elengy Terminal upgr­ade to a bigger floating storage and regas­ification unit and instead recalled original unit — Exquisite — back to work. — Dawn/File

ISLAMABAD: Owing to serious legal risks, the board of directors of the state-run Sui Southern Gas Company (SSGC) on Friday rejected Engro Elengy Terminal (EET) upgr­ade to a bigger floating storage and regas­ification unit (FSRU) and instead recalled original unit — Exquisite — back to work.

The Exquisite FSRU operated by Excelerate Energy of USA had been on dry docking since June 29 for repair and was replaced by a larger FSRU Sequoia since then to ensure LNG supply.

The Petroleum Division and the EET had been trying to retain the Sequoia terminal, having greater re-gasification capacity, on the premise that this would reduce gas shortage in coming winter months. However, this did not materialise as the SSGC board and management were not ready to accept demands to give up legal rights under old contract and increase financial exposure in view of their previous experience that landed many of its executives in National Accountability Bureau custody.

“The board of directors after due deliberation considering the legal, commercial and financial exposures decided that this transaction cannot be undertaken in lieu of the potential exposure and risks,” announced the SSGC after the board meeting.

Rejects replacement of old FSRU with larger unit

Board chairperson Dr Shamshad Akhtar recused to attend the meeting for conflict of interest as she was also on Engro’s board. A couple of other board members were reportedly asked by influential government officials to also excuse but they attended.

When approached for comments, Engro said it was “still awaiting an official response on the matter. Regardless of the response, Engro is prepared and will work with all stakeholders for a smooth way forward for all”, adding it would not comment further.

The SSGC said that Ministry of Energy had advised it to “evaluate the option to replace FSRU Exquisite with a larger size FSRU Sequoia in order to have additional regasification capacity. However, the SSGC after undergoing a proper due diligence has concerns as this would lead to serious exposure and risks for SSGC”.

It also confirmed that the EETL was asking the SSGC to forego its step-in right in case of operators’ default and also waive its option to purchase the FSRU but put on record that “this would be a violation of the LSA (LNG supply agreement) and expose SSGC to potential future risks”.

It also noted that clearance of NAB would be vital. Also the PPRA is not being followed which too can point towards preferential treatment to one terminal operator whereas the other terminal too has surplus capacity available.

Moreover, SNGPL and PSO have not yet committed for utilising the additional capacity and availability of additional LNG cargoes, the SSGC said. “It was agreed that clearance from cabinet to initiate negotiations wou­ld be needed besides NAB’s clearance. These matters were referred to SSGC board for guidance”, it said, adding the board had decided that this transaction could not be undertaken due to the above mentioned risks.

A senior government official said the Exquisite FSRU, after repair, was laden with LNG to move from Qatar and was expected to dock at Port Qasim on Sept 10-12 to replace Sequoia. Until then Sequoia would continue regasification.

In response to Engro’s letter to the government for continuation of Sequoia with the conditions noted above, the Petroleum Division separately wrote to Engro that LNG operations and Services Agreement (LSA) was executed between the EETOL (operator) and SSGC (the customer) which was related to the operation of LNG services infrastructure and provision of LNG services.

“Since it is a bi-party commercial and performance relationship where both parties have defined rights and obligations, therefore, subject needs to be mutually resolved between the parties,” the Petroleum Division told Engro.

Meanwhile, a government official said Pakistan LNG Ltd (PLL) had accepted three bids for LNG cargoes for delivery bet­ween Oct 28 to Nov 12, all at rates above $20.3888 per mmBtu, received through urg­ent tender.

Published in Dawn, September 4th, 2021

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Ties with Tehran
Updated 24 Apr, 2024

Ties with Tehran

Tomorrow, if ties between Washington and Beijing nosedive, and the US asks Pakistan to reconsider CPEC, will we comply?
Working together
24 Apr, 2024

Working together

PAKISTAN’S democracy seems adrift, and no one understands this better than our politicians. The system has gone...
Farmers’ anxiety
24 Apr, 2024

Farmers’ anxiety

WHEAT prices in Punjab have plummeted far below the minimum support price owing to a bumper harvest, reckless...
By-election trends
Updated 23 Apr, 2024

By-election trends

Unless the culture of violence and rigging is rooted out, the credibility of the electoral process in Pakistan will continue to remain under a cloud.
Privatising PIA
23 Apr, 2024

Privatising PIA

FINANCE Minister Muhammad Aurangzeb’s reaffirmation that the process of disinvestment of the loss-making national...
Suffering in captivity
23 Apr, 2024

Suffering in captivity

YET another animal — a lioness — is critically ill at the Karachi Zoo. The feline, emaciated and barely able to...