KARACHI: The repair and rehabilitation work of roads and revamping of drainage system in the SITE area has not yet started despite approval of funds for the work by the Sindh government six months ago, which has worsened the state of infrastructure in the main industrial hub of the country.

In September 2020, the chief minister approved Rs1.037 billion for the said works in the SITE area on demand and protest by industrialists.

These funds were allocated for the reconstruction of 19 roads in SITE.

The KDA was given the job to rehabilitate two of these roads while the remaining 17 roads were to be built under the Karachi Mega City Project.

The revised PC-I of the roads allotted to the KDA has not yet been approved despite the passage of more than three months.

“Under these conditions, it has become very difficult for industrialists to reach their factories. Even pedestrians are facing a lot of difficulties in reaching their destinations. Not only this, many transporters have refused to pick up export consignments from the factories in SITE area while those who agree, demand four times more freight charges. The increase in freight and transportation cost has a direct impact on the cost of production, thereby making exports uncompetitive in the international markets,” said Abdul Hadi, president of the SITE Association of Industry in a statement.

Mr Hadi expressed serious concerns over delay in starting infrastructure restoration work in the SITE area and appealed to the chief minister of Sindh to take notice of the situation and issue directives regarding the uplift work on an urgent basis.

The association chief mentioned that due to completely destroyed infrastructure in the SITE area, incidents of overturning of loaded trucks and vehicles had become a routine which was not only causing financial losses to factories, but also posing a threat to precious lives. He pointed out that many people had suffered injuries in such incidents. In addition, due to rickety roads, robbery incidents have also increased in the area.

Mr Hadi urged the chief minister to take personal interest in resolving the issues of the SITE area and issue immediate orders to the departments concerned to start infrastructure uplift work.

He also appealed to the chief minister of Sindh to issue notification of the oversight committee as per his commitment and give representation to the SITE Association of Industry in the committee for monitoring quality of the uplift work.

Published in Dawn, March 8th, 2021

Opinion

Editorial

Rigging claims
Updated 04 May, 2024

Rigging claims

The PTI’s allegations are not new; most elections in Pakistan have been controversial, and it is almost a given that results will be challenged by the losing side.
Gaza’s wasteland
04 May, 2024

Gaza’s wasteland

SINCE the start of hostilities on Oct 7, Israel has put in ceaseless efforts to depopulate Gaza, and make the Strip...
Housing scams
04 May, 2024

Housing scams

THE story of illegal housing schemes in Punjab is the story of greed, corruption and plunder. Major players in these...
Under siege
Updated 03 May, 2024

Under siege

Whether through direct censorship, withholding advertising, harassment or violence, the press in Pakistan navigates a hazardous terrain.
Meddlesome ways
03 May, 2024

Meddlesome ways

AFTER this week’s proceedings in the so-called ‘meddling case’, it appears that the majority of judges...
Mass transit mess
03 May, 2024

Mass transit mess

THAT Karachi — one of the world’s largest megacities — does not have a mass transit system worth the name is ...