Work yet to start on supply of water from Chahan Dam

Published December 25, 2020
The union councils which will be provided water from the new dam are: Dhamial, Chakra, Girja, Chak Jalaldin 1 and 2, Dhama Syedan, Kilial and Lakhan. — Photo courtesy Kohi Marri/File
The union councils which will be provided water from the new dam are: Dhamial, Chakra, Girja, Chak Jalaldin 1 and 2, Dhama Syedan, Kilial and Lakhan. — Photo courtesy Kohi Marri/File

RAWALPINDI: Chahan Dam is almost complete but no work has been started to supply six million gallon daily (MGD) water from the reservoir to seven union councils of Rawalpindi due to insufficient funds.

Due to the delay, the project cost has increased from Rs5.3 billion to Rs6.7 billion.

The Punjab government approved the project worth Rs5.3 billion to bring six MGD water fromChahan Damin Dec 2018. The damnear Chakri is being constructed on River Sill Kus. It is located 22 km from the garrison city.

A senior official of Water and Sanitation Agency (Wasa) told Dawn that the provincial government had released Rs200 million in the last fiscal year and Rs250 million in the current fiscal year which was insufficient to start the work. He said 150 kanals would be acquired and there was a need of Rs650 million to acquire the land. He said land acquisition was likely to start in the next fiscal year.

He said the Small Dam Organisation had started construction of the spillway and after filling water in the dam construction of the intake chambers would create problems.

According to the plan, an intake chamber at Chahan, a filtration plant at Chakri and a pumping station at Ranyal would be constructed. The official said 80 kanals will be required for the filtration plant and 35 kanals each at Ranyal and Chakara.

The union councils which will be provided water from the new dam are: Dhamial, Chakra, Girja, Chak Jalaldin 1 and 2, Dhama Syedan, Kilial and Lakhan.

According to official figures, at present the water demand of the city having a population of about 1.5 million is 50 MGD. The city relies mainly on Rawal and Khanpurdams in addition to groundwater drawn from 420 tubewells. The total extraction from these sources is 37 MGD (21 from tubewells and 16 MGD from thedams).

When contacted, Wasa spokesman Umer Farooq said the agency had prepared the project to overcome water shortage in the union councils of the defunct Potohar Town.

He said as soon as funds were received from the government, work on the project would be started. He said formal request for the release of funds had already been sent to the government.

Published in Dawn, December 25th, 2020

Opinion

Editorial

Collective security
Updated 12 Mar, 2026

Collective security

ERASING previously defined ‘red lines’, the brutal US-Israeli war on Iran has brought regional states face to...
Spectrum leap
12 Mar, 2026

Spectrum leap

THE sale of 480 MHz of fifth-generation telecom spectrum for $507m is a major milestone in Pakistan’s digital...
Toxic fallout
12 Mar, 2026

Toxic fallout

WARS can leave environmental scars that remain long after the fighting is over. The strikes on Iran’s oil...
Token austerity
Updated 11 Mar, 2026

Token austerity

The ‘austerity’ measures are a ritualistic response to public anger rather than a sincere attempt to reform state spending.
Lebanon on fire
11 Mar, 2026

Lebanon on fire

WHILE the entire Gulf region has become an active warzone, repercussions of this conflict have spread to the...
Canine crisis
11 Mar, 2026

Canine crisis

KARACHI’S stray dog crisis requires urgent attention. Feral canines can cause serious and lasting physical and...