PAC asks govt to stop Neelum-Jhelum surcharge collection

Published September 3, 2020
Mohammad Ashraf, secretary to the water resources ministry, informed the committee that the NJS was being charged at a rate of 10 paisa per unit. — Photo by Kohi Marri/File
Mohammad Ashraf, secretary to the water resources ministry, informed the committee that the NJS was being charged at a rate of 10 paisa per unit. — Photo by Kohi Marri/File

ISLAMABAD: The Public Accounts Committee (PAC) issued a directive on Wednesday to stop the collection of Neelum-Jhelum Surcharge (NJS) through electricity bills.

The PAC, which met under the chairmanship of Rana Tanveer Hussain, was informed by the office of the auditor general that the government was collecting the surcharge even though the Neelum-Jhelum Dam had been completed two years ago.

The government, through a notification on Jan 4, 2008, had imposed the NJS on electricity consumers till Dec 31, 2015.

According to audit officials, the surcharge is still being collected despite lapse of the period.

Mohammad Ashraf, secretary to the water resources ministry, informed the committee that the NJS was being charged at a rate of 10 paisa per unit.

According to him, the government had collected Rs70 billion from consumers after expiry of the period in question.

The PAC unanimously recommended that collection of the surcharge through electricity bills be discontinued as the project had already been completed.

Meeting is informed that dam was completed two years ago

Although some PAC members, including Hina Rabbani Khar and Amir Dogar, called for refund of the excess amount collected from consumers, the PAC chairman said this would open up a Pandora’s box. He, however, issued directives to stop further collection of NJS.

Asked about the legal status of the surcharge, the water resources ministry’s secretary conceded that the NJS was being collected even after expiry of the notified period.

He, however, disclosed that a summary had been moved to rename it as “Diamer-Bhasha Surcharge”.

Senator Mushahid Hussain Syed enquired about the status of the fund established by former chief justice Saqib Nisar for Diamer-Bhasha Dam.

The secretary informed the PAC that so far Rs13 billion had been deposited in the fund. He said the fund was at the disposal of the Supreme Court’s administration.

While the water resources secretary expressed hope that the NJS would be converted into Diamer-Bhasha Dam surcharge, the Water and Power Development Authority (Wapda) chairman, retired Lt Gen Muzammil Hussain, opposed the idea. He said construction of the dam required billions of rupees and it could not be done through crowd funding.

The audit officials were also of the view that levy could only be imposed through an act of parliament and JS could not be reimposed with an alternative nomenclature.

The Neelum-Jhelum hydropower project, constructed on Neelum River in Azad Jammu and Kashmir, has a dam at Nauseri, an underground waterway system consisting of 52-kilometre-long tunnels, and an underground powerhouse at Chattar Kalas. It was commissioned in April 2018.

The Diamer-Bhasha Dam is a reservoir with a height of 272 metres and after completion it will be the tallest roller compact concrete (RCC) dam in the world.

It will have a spillway with 14 gates and five outlets for flushing out silt. The diversion system involves two tunnels and a diversion canal.

The project, with a total outlay of Rs1.4 trillion, is expected to be completed in 2028.

Published in Dawn, September 3rd, 2020

Opinion

Editorial

Removing subsidies
Updated 09 May, 2026

Removing subsidies

The government no longer has the budgetary space to continue carrying hundreds of billions of rupees in untargeted subsidies while the power sector itself remains trapped in circular debt, inefficiencies, theft and under-recovery.
Scarred at home
09 May, 2026

Scarred at home

WHEN homes turn violent towards children, the psychosocial damage is lifelong. In Pakistan, parental violence is...
Zionist zealotry
09 May, 2026

Zionist zealotry

BOTH the Israeli military and far-right citizens of the Zionist state have been involved in appalling hate crimes...
Shifting climate tone
Updated 08 May, 2026

Shifting climate tone

Our financial system is geared towards short-term, risk-averse lending, while climate adaptation and green infrastructure require patient, long-term capital.
Honour and impunity
08 May, 2026

Honour and impunity

THE Sindh Assembly’s discussion on karo-kari this week reminds us of the enduring nature of ‘honour’ killings...
No real change
08 May, 2026

No real change

THE Indian sports ministry’s move to allow Pakistani players and teams to participate in multilateral events ...