NTDC upgrades Port Qasim transmission line

Published May 14, 2019
Initially, there was a plan to replace insulators with RTV coated ones at the line’s 8-9km stretch. — AFP/File
Initially, there was a plan to replace insulators with RTV coated ones at the line’s 8-9km stretch. — AFP/File

LAHORE: National Transmission and Despatch Company (NTDC) has completed work on the insulators of 53km-long 500kV double circuit Port Qasim transmission line with the room temperature vulcanising (RTV) ones enabling the system to feed the power distribution system without any glitches.

“Initially, there was a plan to replace insulators with RTV coated ones at the line’s 8-9km stretch, a portion considered critical due to situation near the sea and the plant. However, it was later planned to replace all insulators with RTV coated ones for better performance,” a senior NTDC official told Dawn on Monday.

The line, which originates from Port Qasim Plant and ends at Hub, connecting Jamshoro-Guddu transmission lines, faced tripping and interrupting power transmission to distribution system since long mainly due to deposition of pollutants emerging from the sea salt impact and fuel emission from the adjacent K-Electric’s oil-fired power plant.

“Insulators play an important role in transmission lines as whenever there was pollution, the insulation level decreased.

“It happens when some stick material falls on the insulators as a result of a mixture of emissions and air moisture. Therefore, the final resolution to avert tripping of the lines in such areas is to replace the normal insulators with RTV ones,” he explained.

The coating, he said, prevents the material from sticking to insulator surface. It is a preferred solution worldwide and reduces chances of tripping. Moreover, it also reduces continuous labour of washing the lines.

“Besides this, various works on removing various system constraints at 220/132kV Nowshera Grid Station, augmentation of the transformer at 220kV Quetta, 220kV twin bundled NKLP-Wapda town line and augmentation of transformers at 500kV Shikarpur and 220kV Sarfraz Nagar grids have also been completed,” he claimed.

Published in Dawn, May 14th, 2019

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Rigging claims
Updated 04 May, 2024

Rigging claims

The PTI’s allegations are not new; most elections in Pakistan have been controversial, and it is almost a given that results will be challenged by the losing side.
Gaza’s wasteland
04 May, 2024

Gaza’s wasteland

SINCE the start of hostilities on Oct 7, Israel has put in ceaseless efforts to depopulate Gaza, and make the Strip...
Housing scams
04 May, 2024

Housing scams

THE story of illegal housing schemes in Punjab is the story of greed, corruption and plunder. Major players in these...
Under siege
Updated 03 May, 2024

Under siege

Whether through direct censorship, withholding advertising, harassment or violence, the press in Pakistan navigates a hazardous terrain.
Meddlesome ways
03 May, 2024

Meddlesome ways

AFTER this week’s proceedings in the so-called ‘meddling case’, it appears that the majority of judges...
Mass transit mess
03 May, 2024

Mass transit mess

THAT Karachi — one of the world’s largest megacities — does not have a mass transit system worth the name is ...