Electricity evacuation issues in Patrind hydropower project

Published January 1, 2019
The 147MW Patrind hydropower project, located on the boundary of Azad Jammu and Kashmir and Khyber-Pakhtunkhwa, could produce only 480GWh against the annual target of 632GWh since it went into commercial operation in November last year. ─ File photo
The 147MW Patrind hydropower project, located on the boundary of Azad Jammu and Kashmir and Khyber-Pakhtunkhwa, could produce only 480GWh against the annual target of 632GWh since it went into commercial operation in November last year. ─ File photo

ISLAMABAD: The run-of-river Patrind hydropower project, which has now completed its first year of commissioning, is facing issues to evacuate electricity to the national grid, as the National Transmission Distribution Company (NTDC) is yet to lay transmission from power house to the main grid station in Mansehra.

The 147MW Patrind hydropower project, located on the boundary of Azad Jammu and Kashmir and Khyber-Pakhtunkhwa, could produce only 480GWh against the annual target of 632GWh since it went into commercial operation in November last year.

Due to the lack of direct transmission circuit, the national exchequer is facing loss of millions of rupees. The project is currently shut down mode for two months (December-January) for carrying out maintenance work.

The Patrind project was completed in four years, starting in 2012, at a cost of $436 million. The ADB provided assistance of $97m and it was constructed on build-own-operate-transfer (BOOT) basis for a period of thirty years from the commercial operation date.

Five more run-of-river hydropower projects, originating from Kaghan, are: Suki Kinari, a CPEC-merged project, Balakot hydropower, Neelum-Jhelum, Kohala, Gulpur and New Bong.

The Patrind hydropower station is currently under-performing due to weak transmission network through Muzaf­­farabad-Hattian-Mangla-Jheum-Rawat — a long circuit that trips frequently due to weak circuit, Habibur Rehman Khan, a project engineer, explained.

He said that the closest inter-connection of Patrind will be Muzaffarabad-Mansehra-Abbottabad-Islamabad circuit and there will be no circuit in between without causing tripping. The Hattian network is quite old and complex and not suitable for evacuating power from Patrind, he added.

To evacuate electricity, NTDC intends to lay 132kV transmission line, using rail conductor of 45km from Patrind project to Mansehra new 132kV grid station in the first phase. One of these circuits would be direct while the other would be looped in and out at Balakot 132kV substation, with Patrind-Balakot 32km long and Balakot-Mansehra 23km.

Patrind hydropower project is one of the two power projects set up by the ‘Korea Water Resources Corpora­tion’. The second one will be 102MW Gulpur power project.

Published in Dawn, January 1st, 2019

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Missing links
Updated 27 Apr, 2024

Missing links

As the past decades have shown, the country has not been made more secure by ‘disappearing’ people suspected of wrongdoing.
Freedom to report?
27 Apr, 2024

Freedom to report?

AN accountability court has barred former prime minister Imran Khan and his wife from criticising the establishment...
After Bismah
27 Apr, 2024

After Bismah

BISMAH Maroof’s contribution to Pakistan cricket extends beyond the field. The 32-year old, Pakistan’s...
Business concerns
Updated 26 Apr, 2024

Business concerns

There is no doubt that these issues are impeding a positive business clime, which is required to boost private investment and economic growth.
Musical chairs
26 Apr, 2024

Musical chairs

THE petitioners are quite helpless. Yet again, they are being expected to wait while the bench supposed to hear...
Global arms race
26 Apr, 2024

Global arms race

THE figure is staggering. According to the annual report of Sweden-based think tank Stockholm International Peace...