After snags, new gas power plants may start by March

Published January 30, 2018
GE claims its state-of-the-art turbines are highly fuel-efficient and long-lasting. They are being installed in three power plants in Punjab under the CPEC framework.
GE claims its state-of-the-art turbines are highly fuel-efficient and long-lasting. They are being installed in three power plants in Punjab under the CPEC framework.

LAHORE: The three recently-built combined-cycle gas-fired power plants in Punjab are facing production delays of up to two-and-a-half months because of a “variety of factors”, including but not limited to problems with the world’s most efficient gas turbines.

Conversations with the senior management of the two public companies – National Power Parks Management Company and Punjab Thermal Power – created for establishing these power stations show that the commercial operations date (COD) of all the stations has now been pushed back to early March 2018. All three have been hit by delays throughout their construction.

Late delivery of gas turbines, combustion seal leak at one of the turbines at Bhikki and severe damage caused to a turbine at Haveli Bahadur Shah are some of the major factors that have contributed to commercial production delays, according to the senior management members Dawn spoke with.

Once fully operational, the three plants at Bhikki (Sheikhupura), Baloki (Kasur) and Haveli Bahadur Shah (Jhang) have the capacity to together generate more than 3,600 megawatts of electricity. The first two plants were originally scheduled to start commercial operations last month and the third one was billed to start supplying electricity to the national grid earlier this month.

Delayed delivery and technical issues hit the LNG-fired generators all last year

The Bhikki power station is being financed by the government of Punjab and the other two by the federal government. Punjab recently inaugurated another gas-fired power plant at Haveli Bahadur Shah with a nameplate generation capacity of 1,263 megawatt to be completed early 2020. With Chinese companies executing the projects as EPC (engineering, procurement and construction) contractors, GE is providing its flagship gas turbines with fuel efficiency of between 61.63pc to 62.5pc for them.

The plants are all part of the China Pakistan Economic Corridor (CPEC) initiative.

“Moreover, the RLNG (regassified liquefied natural gas) supply to the plants remained suspended for around three weeks, leading to delays in fuel testing,” Ahad Cheema, the chief executive officer of the Punjab Thermal Power Ltd, told this reporter.

“We are facing what is known as launch issues, which are not uncommon with large, complex power plants of this size before their commissioning for commercial production. Nowhere in the world has a power plant of this size been completed, say, in 40 months let alone in 27 months, the time given to us to start commercial production,” Cheema argued. “It’s going to be a world record when these plants come online in such a short time.”

A senior GE executive told Dawn that the company had done its part of the job, resolved all issues faced by the turbines and was moving ahead according to the schedule of ECP contractors.

A National Power Parks Management Company official said the federal and provincial power stations were undergoing fuel testing at the moment and will not be available for commercial operations before first week of March. “Once we are done with our test-runs with backup fuel – diesel – the plants will be linked with the national grid well before peak summer”, he added.

Published in Dawn, January 30th, 2018

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Afghan turbulence
Updated 19 Mar, 2024

Afghan turbulence

RELATIONS between the newly formed government and Afghanistan’s de facto Taliban rulers have begun on an...
In disarray
19 Mar, 2024

In disarray

IT is clear that there is some bad blood within the PTI’s ranks. Ever since the PTI lost a key battle over ...
Festering wound
19 Mar, 2024

Festering wound

PROTESTS unfolded once more in Gwadar, this time against the alleged enforced disappearances of two young men, who...
Defining extremism
Updated 18 Mar, 2024

Defining extremism

Redefining extremism may well be the first step to clamping down on advocacy for Palestine.
Climate in focus
18 Mar, 2024

Climate in focus

IN a welcome order by the Supreme Court, the new government has been tasked with providing a report on actions taken...
Growing rabies concern
18 Mar, 2024

Growing rabies concern

DOG-BITE is an old problem in Pakistan. Amid a surfeit of public health challenges, rabies now seems poised to ...