LAHORE: In a significant development regarding hydel resources in the country, construction work on the 4,320-megawatt Dasu hydropower project will commence within a week, as civil works contractor has been mobilised for the purpose.

During his visit to the project site on Wednesday, Chairman of the Water and Power Development Authority (Wapda) retired Lt Gen Syed Muzammil Hussain said: “Commencement of the Dasu project’s construction is going to be a good omen for development of hydropower potential in the country, as the mega-scheme is being constructed by leveraging Wapda’s financial strength.”

According to a press release issued by the authority, Mr Hussain visited the site to review progress made regarding infrastructure development and resettlement activities leading to socio-economic uplift of the population concerned.

The Wapda chairman said that of the $4.2 billion required for completion of the first phase of the project, the World Bank’s International Development Association (IDA) was providing a credit of $824 million, while the rest of the amount was being arranged by the authority from various commercial sources.

Expressing satisfaction over the financial arrangement for construction of the project, he said that Wapda ventured into the international financial market last week to secure $350m at a very competitive rate as it staggered draw down to suit the project’s financing requirements.

The amount was raised with partial guarantee of the World Bank (IDA) and the rest with the sovereign guarantee of the government.

“The successful financing is a testament to the confidence reposed by the international financial institutions in the credit worthiness of Wapda. Apart from this [financing], Wapda has already arranged local financing for the project worth Rs144bn from a consortium of local banks,” said Mr Hussain.

The 4,320MW Dasu hydropower project is being built by Wapda on the Indus, upstream of Dasu town, in Kohistan district of Khyber Pakhtunkhwa.

The project will be completed in two phases — each stage having a power generation capacity of 2,160MW.

Published in Dawn, July 6th, 2017

Opinion

Editorial

Chinese diplomacy
Updated 14 Mar, 2026

Chinese diplomacy

THERE are signs that China is taking a more active role in trying to resolve the issue of cross-border terrorism...
Fragile gains at risk
14 Mar, 2026

Fragile gains at risk

PAKISTAN is confronting an external shock stemming from the US-Israel war on Iran that few of the other affected...
Kidney disease
14 Mar, 2026

Kidney disease

ON World Kidney Day this past Thursday, the Pakistan Medical Association raised the alarm on Pakistan’s...
Delicate balance
Updated 13 Mar, 2026

Delicate balance

PAKISTAN has to maintain a delicate balance where the geopolitics of the US-Israeli aggression against Iran are...
Soaring costs
13 Mar, 2026

Soaring costs

FOR millions of households already grappling with Ramazan inflation, the sharp increase in petrol and diesel prices...
Perilous lines
13 Mar, 2026

Perilous lines

THE law minister’s veiled warning to the media to “exercise caution” and not cross “red lines” while...