GUJRANWALA: When the government had approved the the construction of a district government’s parking plaza on GT Road in Gujranwala in 2014, its estimated cost was Rs270 million.

As the construction was done at a slow pace, the 11-storey plaza is still incomplete and now its cost has increased to Rs490 million, according to reports.

The city district government started construction of the parking plaza to facilitate the vehicle owners, and it was to be built in one year (2015). The first two storeys were for offices and shops and the remaining nine for the parking of vehicles.

The plaza was to be ready by March 30, 2015, but its deadline was extended to March 30, 2016.

The delay increased estimated cost from Rs270 million to Rs490 million.

District Coordination Officer Muhammad Aamir Jan ordered an inquiry into the delay, but the inquiry report is also suffering delays.

Published in Dawn, April 27th, 2016

Opinion

Editorial

Under siege
Updated 03 May, 2024

Under siege

Whether through direct censorship, withholding advertising, harassment or violence, the press in Pakistan navigates a hazardous terrain.
Meddlesome ways
03 May, 2024

Meddlesome ways

AFTER this week’s proceedings in the so-called ‘meddling case’, it appears that the majority of judges...
Mass transit mess
03 May, 2024

Mass transit mess

THAT Karachi — one of the world’s largest megacities — does not have a mass transit system worth the name is ...
Punishing evaders
02 May, 2024

Punishing evaders

THE FBR’s decision to block mobile phone connections of more than half a million individuals who did not file...
Engaging Riyadh
Updated 02 May, 2024

Engaging Riyadh

It must be stressed that to pull in maximum foreign investment, a climate of domestic political stability is crucial.
Freedom to question
02 May, 2024

Freedom to question

WITH frequently suspended freedoms, increasing violence and few to speak out for the oppressed, it is unlikely that...