Sahiwal coal-fired power plant: Builders expect power generation before deadline

Published
13

LAHORE: Chinese companies building the 1,320MW Sahiwal coal-fired power plant, the first-ever such a project in Pakistan, expect power generation next year which will be the ‘cheapest’ in terms of tariff and environment friendly.

Though the consortium of two Chinese companies which started work on June 9, 2015, is raising basic infrastructure at over a thousand acre land reserved for the plant with an official target of completing it by Dec 25, 2017, officials say the provincial chief executive wants it to be completed much earlier.

Around 3,000 workers, including 1,000 Chinese, are working at the site which is guarded by police personnel.

“We are going to offer 8.1 cents per electricity unit to the Pakistani government under an agreement with the National Electric Power Regulatory Authority and this is the cheapest rate in Pakistan”, says Song Taiji, the Chief Executive Officer of Humeng Shandong Ruyi (Pakistan) Energy (Pvt) Limited.

He told Lahore-based reporters at the site on Friday that the company would produce and sell the electricity for 30 years on a BOT basis before handing over the plant to the Punjab government. He said average life of the plant was 30 years approximately.

Song said the upfront tariff was agreed after Nepra involved international experts and bidding process. He said the plant was being constructed with an estimated cost of $1.8 billion jointly sponsored by two Chinese companies.

He said the coal-fired power generation was much popular in China as more than 80 per cent electricity production came from coal there.

Song said the reason behind importing coal from Indonesia and South Africa was the non-availability of standard coal in Pakistan. “Though Pakistan has huge reserves of indigenous coal but we cannot use them at the moment because of absence of excavation technology and quality material”, he added.

He said the coal would be transported from Port Qasim, Karachi, to the site via rail while canal water with the help of a reservoir would be used in the power generation process. To a question, Song claimed the solar power was costlier than coal’s.

He said the super critical technology would be used in the plant which required high temperature for the perimeter of steam and less coal consumption.

Regarding environmental concerns, he said the height of the Chimney had been set at 180 meters for safe emission.

He said two per cent component of sulphur dioxide in the imported coal would be brought down to zero level to avoid environmental hazards. “We will have proper sulphurization process in the plant for less carbon emission.”

Song further said plants having capacity of more than 300MW fell in the category of super critical technology, adding in Pakistan the coal generation share was even less than one per cent compared to developed countries where share of electricity from coal was about 50 per cent, which meant more environmental pollution.

Song, whose company is the largest in China to generate coal-fired electricity, said he had security concerns before coming to Pakistan last year but now he was comfortable.

“We now feel secure in Punjab and will continue our work without any fear. I rate Pakistan as my second hometown”, Song told a questioner.

Asked why coal-fired technology was being introduced in Punjab when it was becoming redundant in other countries of the world, he said coal-fired power was not an old-fashioned rather it was very advance technology being used by China and other countries.

“This plant is not sub-critical rather super critical which burns less coal and gives less emission as for as environmental protection is concerned.”

Nadeem Aslam Chauhdry, who is energy coordinator for the Punjab government, told reporters that the chief minister had asked the company to complete the plant much earlier than the deadline. “We cannot give you the exact date but we are determined to do the job in less than two and half years.”

He said the federal government had announced upfront tariff for the coal power projects and the company had accepted the tariff of 8.1 cents per unit irrespective of its cost estimates.

He claimed the tariff would not remain exactly 8.1 cents in future as, at the time of agreement, the cost of coal was $ 120 per ton and it was now $60 per ton which implied that the power tariff was the cheapest for this plant as compared to other fossil fuels.

Chauhdry told a questioner that an army brigade was being raised to secure projects linked with the China Pakistan Economic Corridor and this power plant also included in the CPEC.

Published in Dawn, January 2nd, 2016

Opinion

Editorial

Muddled hierarchy
Updated 15 Nov, 2026

Muddled hierarchy

The jurisdiction of the two courts and a mechanism for settling disputes between them should be spelt out in law, not left to judges to fight over.
Growing crisis
15 Nov, 2026

Growing crisis

AN emergency can be judged by the speed with which it draws an effective response. The National Population Council’s...
Organised rackets
15 Nov, 2026

Organised rackets

ON the International Day against Transnational Organised Crime, observed today, Pakistan finds itself in a tight...
Referendum talk
Updated 14 Nov, 2026

Referendum talk

Unless the PPP is deliberately using Sindh as a bargaining chip, it should issue a clarification with a clear, consistent position on new administrative units, not one tailored to protect its home turf.
Mineral wealth
Updated 14 Nov, 2026

Mineral wealth

Minerals should not be presented as a solution to Pakistan’s long-term economic difficulties. The aim should be to build an industrial base rather than export raw materials.
Late diagnosis
14 Nov, 2026

Late diagnosis

AS we mark World Diabetes Day today, Pakistan faces a troubling question: how many people are living with diabetes...