ISLAMABAD: The state council of the People's Republic of China granted approval for an investment of $1.2 billion in the surface mining of Thar coal and the establishment of 660 MW power projects, as part of the China-Pakistan Economic Corridor project (CPEC).

The final lending documents in this regard will be signed on December 21 in Beijing.

According to details shared on Wednesday, China's state council for financing gave final nod for establishment of 660 MW Power Plant on indigenous coal in Thar Block-II and the surface mining of 3.8 MTPA (million tonnes per annum of Thar coal.

Earlier, in October, the Chinese government had agreed to increase the financing of Thar Coal project to double the generation capacity of Thar Block-II from 660 to 1,320MW, and to add project capacity and increase the mine size from 3.8 to 6.5 million tonnes per annum as part of the priority list of CPEC projects.

In a letter addressing Secretary Ministry of Water and Power Muhammad Younus Dagha, the Chinese side confirmed the approval of financing of mega project by China's state council.

Sinosure in collaboration with Sindh Engro Mining Company are jointly undertaking Surface Mining of 3.8 MTPA and establishment of 660 MW Power Plan projects in Thar Block-II which is part of China Pakistan Economic Corridor (CPEC) projects.

According to the ministry, reaching this stage of collaboration is considered as a major achievement in shortest time.

Arrangement of finances and completion of lending documents is the most critical part in any project which signifies starting of actual work on the projects.

This project was on the government's priority list which helped it reach the advanced stage among other CPEC mega projects, after signing of CPEC energy projects agreement in November, 2014.

It is worthy to mention that due to tireless efforts of Ministry of Water and Power and NEA China, all the regulatory requirements have been completed in one year's time.

Thar Coal has remained on agenda of every government, however, practical steps have been taken by the Ministry for first time since present government focused on tapping potential to its fullest.

Follow Dawn Business on X, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

The May war
06 May, 2026

The May war

A YEAR since India launched unprovoked attacks against Pakistan using the Pahalgam tragedy as an excuse, and this...
Looking inwards
06 May, 2026

Looking inwards

REGULAR appraisals by human rights groups and activists should not be treated by the authorities as attempts to ...
Feeling the heat
06 May, 2026

Feeling the heat

ANOTHER heatwave season has begun, and once again, the state is scrambling to respond to conditions it has long been...
Energy shock
Updated 05 May, 2026

Energy shock

The longer the crisis persists, the more profound its consequences will be.
Unchecked HIV
05 May, 2026

Unchecked HIV

PAKISTAN’S HIV surge is no longer a slow-burning public health concern. It is now a system failure unfolding in...
PSL thrills
05 May, 2026

PSL thrills

BY the end of it all, in front of fans who had been absent for almost the entire 11th season of the Pakistan Super...